Repair Design Furniture

Abstract technology of repair and maintenance of an asynchronous motor with a squirrel-cage rotor. Technological map of repair of windings of an induction motor Technological map of repair of an induction motor

Tool used

In the process of servicing and repairing an asynchronous squirrel cage motor, the following tool is used:

Reconciliation ruler

Staples and strings

Rulers for pulleys of different widths.

Spanners 6 - 32 mm - 1 set.

Files - 1 set.

Head set - 1 set.

Metal brush - 1 pc.

Plumber's knife - 1 pc.

Screwdriver set - 1 set.

Bench screwdriver - 1 pc.

Dies 4 - 16 mm - 1 set.

Taps 4 - 16 mm - 1 set.

Drill set 3 - 16 mm - 1 set.

Crowbar - 1 pc.

Pliers - 1 pc.

Chisel - 1 pc.

Drill - 1 pc.

Kern - 1 pc.

Flat brush - 2 pcs.

Hammer - 1 pc.

Shovel - 1 pc.

Broom brush - 1 pc.

Technological map of repair and maintenance of an asynchronous motor with a squirrel-cage rotor

Name and content of works

Equipment and fixtures

Technical requirements

External inspection of the electrical machine, including control systems, protection, ventilation and cooling.

Compliance with technical data sheets for operation and electrical circuits.

Visual check of the condition of the grounding conductor; checking the condition of the ground loop.

Hammer, shovel

Lack of anti-corrosion coating, loosening of fastening, mechanical damage are not allowed.

Check for extraneous noise.

Extraneous noise is not allowed.

Cleaning accessible parts from dirt and dust.

White spirit, rags, metal brush, broom brush.

Inspection of the elements of the connection between the engine and the driven mechanism.

Cracks at the seams, breaks, distortions, loosening of threaded connections are not allowed.

Checking the connection and the reliability of the sealing of the supplied cables, the technical condition and tightness of the lead-in boxes and couplings of the sealed lead-in; checking the condition of seals, surfaces and parts that ensure explosion protection; explosion proof of cable and wire entries.

A set of locksmith probes No. 1 A set of tools a set of screwdrivers A set of heads.

Roughness of the working surface Rd no more than 1.25 microns.

Checking the fastening of the electric drive to the frame (valve).

Set of tools. Set of heads.

Loosening of the fastening is not allowed.

Inspection of the state of the start-up control equipment (PRA).

Blowing out the stator and rotor with compressed air.

Compressor.

Insulation resistance test of windings; drying if necessary.

Megohmmeter with a voltage of 500V.

Insulation resistance should not be less than 0.5 MΩ.

Checking the mating of parts that ensure tightness.

A set of locksmith probes No. 1. A set of tools, a set of screwdrivers. Set of heads, sealant.

The clearances are indicated in the instruction manual.

Checking the presence of grease in the bearings of the electric motor (if there is a press oiler, replenishment).

CIATIM-221 grease, grease press-in gun.

Set of tools. Screwdriwer set.

Brush, paint (plate).

Inspection, cleaning and tightening of contact connections.

Set of tools. Cloth abrasive paper in accordance with GOST 5009-82.

Distortions, the presence of oxide, loosening of contact connections are not allowed.

Revision of automatic circuit breaker assemblies.

Set of tools. Screwdriwer set.

Checking the presence of cable markings, inscriptions and markings on the casing, restoration if necessary.

Brush, paint (plate).

The absence of markings and inscriptions is not allowed.

Security measures

The electric motor must be de-energized, disconnected AB, installed grounding, posted posters. Apply portable grounding to the lead-in ends of the motor cable. Protect the place of work. Work with PPE. Work with verified devices and tested power tools and devices.

The composition of the brigade

An electrician for the repair of electrical equipment with an electrical safety group of at least the third. Electrician for the repair of electrical equipment with the third group of electrical safety.

Technological (map) process during the repair of a high-voltage synchronous electric motor weighing 2 tons. Outfit, turning off the electric motor, taking out for repair, using lifting mechanisms, slinging scheme, rigging to the repair site

Architecture, design and construction

If work on an electric motor or a mechanism driven by it is associated with touching live and rotating parts, the electric motor must be turned off with the implementation of the provided technical measures to prevent its erroneous activation. Work that is not associated with touching live or rotating parts of the electric motor and the mechanism driven by it can be performed on a running electric motor. When working on an electric motor, it is allowed to install grounding on any section of the cable line ...

Technological (map) process during the repair of a high-voltage synchronous electric motor weighing 2 tons. Outfit, turning off the electric motor, taking out for repair, using lifting mechanisms, slinging scheme, rigging to the repair site.

If work on an electric motor or a mechanism driven by it is associated with touching live and rotating parts, the electric motor must be turned off with the implementation of the provided technical measures to prevent its erroneous activation. In this case, for a two-speed electric motor, both power circuits of the stator windings must be disconnected and disassembled.

Work that is not associated with touching live or rotating parts of the electric motor and the mechanism driven by it can be performed on a running electric motor.

It is not allowed to remove the guards of the rotating parts of the operating electric motor and mechanism.

When working on an electric motor, it is allowed to install grounding on any section of the cable line connecting the electric motor to the switchgear section, shield, assembly. If work on the electric motor is designed for a long period of time, is not performed or interrupted for several days, then the cable line disconnected from it must also be grounded on the motor side. In cases where the cross-section of cable conductors does not allow the use of portable grounding, for electric motors with voltages up to 1000 V, it is allowed to ground the cable line with a copper conductor with a cross-section of at least the cross-section of the cable conductor, or to connect the cable conductors together and isolate them. Such grounding or connection of cable cores should be taken into account in the operational documentation along with portable grounding.

Before being allowed to work on electric motors capable of rotating due to mechanisms connected to them (smoke exhausters, fans, pumps, etc.), the handwheels of shut-off valves (valves, valves, gates, etc.) must be locked. In addition, measures have been taken to brake the rotors of electric motors or disengage couplings.

The necessary operations with shut-off valves must be agreed with the shift supervisor of the technological shop, section with an entry in the operational log.

The voltage must be removed from the circuits of manual remote and automatic control of electric drives of shut-off valves, guide vanes. On the steering wheels of valves, gates, valves, posters should be posted "Don `t open! People work ", and on the keys, control buttons for electric drives of shut-off valves - "Do not turn on! People work "... On electric motors of the same type or similar in size, installed next to the engine on which the work is to be performed, posters should be posted“Stop! Voltage"regardless of whether they are in operation or stopped.

Admission to all pre-prepared workplaces, one at a time on electric motors of the same voltage, is allowed to be performed simultaneously, registration of a transfer from one workplace to another is not required. At the same time, testing or putting into operation any of the electric motors listed in the order until the complete completion of work on others is not allowed.

The order of turning on the electric motor for testing should be as follows:the contractor removes the team from the place of work, draws up the completion of the work and hands over the outfit to the operational personnel;

operating personnel removes the installed grounding, posters, assembles the circuit.

After testing, if it is necessary to continue working on the electric motor, the operating personnel again prepares the workplace and the team, along with it, is again allowed to work on the electric motor.

Work on a rotating electric motor without contact with live and rotating parts can be carried out by order.

Maintenance of the brush set on a running electric motor is allowed by order of an employee trained for this purpose, having group III, subject to the following precautions:

work with the use of face and eye protection, in buttoned overalls, being careful not to be caught by rotating parts of the electric motor;

use dielectric galoshes, carpets;

do not touch with your hands simultaneously live parts of two poles or live and grounding parts.

The rotor rings are allowed to be ground on a rotating electric motor only with the help of pads made of insulating material.

The labor protection instructions of the relevant organizations should detail the requirements for the preparation of the workplace and the organization of safe work on electric motors, taking into account the types of electrical machines used, the features of ballasts, the specifics of mechanisms, technological schemes, etc.

Organizational measures to ensure the safety of work in electrical installations are:

registration of work by order, order or list of work performed in the order of current operation;

admission to work;

supervision during work;

registration of a break in work, transfer to another place, completion of work.

Responsible for the safe conduct of work are:

issuing an order, giving orders, approving a list of works performed in the order of current operation;

responsible work manager;

admitting;

work manager;

watching;

members of the brigade.


And also other works that may interest you

18424. Classification and general characteristics of the means of obtaining information 36.5 KB
Lecture 9. Classification and general characteristics of the means of obtaining information. Reliable and efficient operation of automation systems is primarily determined by the reliability of the information received about the control object. Receiving in the process control system accurate timely complete ...
18425. Measuring transducers (sensors) 80 KB
Lecture 10. Measuring transducers, sensors. As you already know, a technical means for measuring a particular quantity, which includes a constructive set of a number of measuring transducers and is located directly at the measurement object ...
18426. Classification of pressure measuring instruments. General industrial pressure transmitters 116 KB
Lecture 11. Classification of pressure measuring instruments. General industrial pressure transmitters. Classification of pressure measuring instruments. For direct measurement of the pressure of a liquid or gaseous medium with the display of its value directly on ...
18427. Automatic flow measurement of liquid and gaseous products and bulk media 237 KB
Lecture 12. Automatic measurement of the flow rate of liquid and gaseous products and bulk media. The flow rate of a substance is characterized by the volumetric or mass quantity of the substance passing through a certain section of the channel of the pipeline of the weir flow, etc. per unit time
18429. Methods and means of automatic measurement of the level of liquid and bulk materials in technological processes of mining 145.5 KB
Lecture 13. Methods and means of automatic measurement of the level of liquid and bulk materials in technological processes of mining The level as a physical quantity is measured in units of length of the SI system in meters m international designation m Russian designation ...
18430. Means of information transmission. Communication lines 44.5 KB
Lecture 14. Means of information transmission. Communication lines. Control and management of objects in the process control system occurs by transmitting measuring and command information over certain distances. The transfer of information to the place of its consumption should be carried out with a minimum ...
18431. Means of measurement and presentation of information 31 KB
Lecture 15. Means of measurement and presentation of information. Means of measurement and presentation of information. Devices of this group are intended for the visual presentation of information to a human operator and for issuing signals to a group of special equipment
18432. Analog and digital secondary GSP devices 67 KB
Lecture 16. Analog and digital secondary devices GSP. Devices for issuing information. Distinguish between analog and discrete methods of issuing measurement information. In both cases, the simplest form of display is the display of measurement results on a visual readout.

By clicking on the "Download archive" button, you will download the file you need for free.
Before downloading this file, remember about those good abstracts, tests, term papers, theses, articles and other documents that are unclaimed on your computer. This is your work, it must participate in the development of society and benefit people. Find these works and submit to the knowledge base.
We and all students, graduate students, young scientists who use the knowledge base in their studies and work will be very grateful to you.

To download an archive with a document, in the field below, enter a five-digit number and click the "Download archive" button

Similar documents

    Design of a three-phase asynchronous electric motor with a squirrel-cage rotor. The choice of the analogue of the motor, size, configuration, material of the magnetic circuit. Determination of the stator winding factor, mechanical calculation of the shaft and rolling bearings.

    term paper, added 06/29/2010

    Features of the development of an asynchronous electric motor with a squirrel-cage rotor of the 4A160S4U3 type based on a generalized machine. Calculation of the mathematical model of an induction motor in the Cauchy form 5. Adequacy of the model of direct start of an induction motor.

    term paper, added 04/08/2010

    The principle of operation of the control circuit of an asynchronous motor with a squirrel-cage rotor from one switching point. Reversible time-delayed squirrel-cage induction motor control. Inclusion of an asynchronous motor with a wound rotor.

    test, added 11/17/2016

    Designing and performing the necessary calculations for an asynchronous electric motor with a squirrel-cage rotor with a power of 200 kW, selection of sizes. Modeling the engine, choosing a control scheme. Comparison of the designed engine with an analogue.

    term paper added 09/28/2009

    Calculation of the main dimensions of a three-phase asynchronous motor. Stator winding design. Calculation of the air gap and geometrical dimensions of the rotor tooth zone. Induction motor parameters in nominal mode. Heat and ventilation calculation.

    term paper, added 02/26/2012

    Design of a three-phase asynchronous motor with a squirrel-cage rotor according to technical data. Requirements for the values ​​of efficiency, power factor, slip, frequency of starting current, starting and maximum torque. Choice of engine sizes.

    term paper, added 02/22/2012

    The main problems associated with the construction of a sensorless vector electric drive. Technical data of an asynchronous three-phase squirrel-cage motor, calculation of the parameters of its equivalent and structural diagrams. Calculation of motor speed.

    term paper added on 04/09/2012

Page 10 of 17

3.11 Technological map of current repair of asynchronous electric motors 6kV PEN.

Name of operations

NTD (drawings etc.)

Control operations

Note

Criteria

3.11.1 Disassembly of the electric motor.

Remove the stator terminal cover, disconnect the power cable and RTD wires, disconnect the ground

OVK.412.106 TO

Clean surface of terminals, Integrity of insulators and thread of studs, tight fit of lugs on cables

hot-smoked 12x13 sandpaper, gasoline, soldering iron

Oxidation of terminal surfaces, cracking of insulators, thread stripping on pins, loss of fastening of lugs on cables

Grind the surface of the terminals, rinse with gasoline, if necessary replace the insulators, solder the tips

Disconnect and remove diffusers from the ED.

OVK.412.106 TO

Remove air filter, blow out and dry

OVK.412.106 TO

Blower device, gasoline B-70, g / c 10x12

3.11.2 Revision of the stator.

Check the fastening (from the outside) of the stator ventilation spacers

OVK.412.106 TO

OK by tapping with a hammer

Uniform, dull sound and no rattling

Hammer 0.2 kg

Loose mount

Weld up defective spacers

Remove dust, dirt, oil and inspect the stator winding frontal parts

OVK.412.106 TO

Contamination-free, tight banding and spacer fit

Loose bands and struts

Re-band the winding ends, install spacers

3.11.3 Assembling the electric motor.

Install diffusers on ED.

OVK.412.106 TO

Install the air filter.

OVK.412.106 TO

Connect the power cable, RTD wires, connect the ground, close the cover of the stator terminals,

OVK.412.106 TO

Clean the surface of the terminals, rinse with gasoline, replace the insulators if necessary, solder the tips

After assembly, make a control measurement of the motor insulation resistance and absorption coefficient with a 2500V megohmmeter. The insulation resistance must be at least 40 megohms, the absorption coefficient must be at least the value specified in paragraph 1.3.2.

3.12 Technological map of current repair of asynchronous electric motors 6kV TsN.

Name of operations

NTD (drawings etc.)

Control operations

Fixtures, tools, equipment

Possible defects, malfunctions

Note

Criteria

3.12.1 Disassembly of the electric motor.

Remove the stator terminal cover, disconnect the power cable and RTD wires, disconnect the ground

Clean surface of terminals, Integrity of insulators and thread of studs, tight fit of lugs on cables

hot-smoked, sandpaper, gasoline, soldering iron

Oxidation of terminal surfaces, cracking of insulators, thread stripping on pins, loss of fastening of lugs on cables

Grind the surface of the terminals, rinse with gasoline, if necessary replace the insulators, solder the tips

Measure the air gap between stator and rotor

Set of test leads

Make a decision to transfer the engine to KR to set the required air gap.

3.12.2 Revision of the stator.

Clean the ventilation ducts, bores, winding ends, stator housing from dirt and blow out with compressed air

Air blower, lint-free cloth

Contamination-free, tight banding and spacer fit

Bandage needle, bandage tape

Re-band the winding ends, install spacers

3.12.3 Assembling the electric motor.

Measure the air gap between stator and rotor

Compliance of the clearances with the requirements (Table 4.1).

Set of test leads

Inconsistency of the air gap with the required values

Make a decision to transfer the engine to KR to set the required air gap.

Connect the power cable, RTD wires, connect the ground, close the cover of the stator terminals,

Clean surface of terminals, Integrity of insulators and thread of studs, tight fit of lugs on cables

hot-smoked, sandpaper, gasoline, soldering iron

Oxidation of terminal surfaces, cracking of insulators, thread stripping on pins, loss of fastening of lugs on cables

Clean the surface of the terminals, rinse with gasoline, replace the insulators if necessary, solder the tips

After assembly, make a control measurement of the motor insulation resistance and absorption coefficient with a 2500V megohmmeter. The insulation resistance must be at least 40 megohms, the absorption coefficient must be at least the value specified in paragraph 1.3.2. When assembling, check the condition of the oil gauges, for which:

a) clean the oil indicators from external contamination;

b) unscrew the damping bolt from the oil gauge, clean the inner cavity of the damping chamber of the oil gauge and the damping bolt from dirt; install a new gasket for the damping bolt head and screw the bolt back. It is allowed, if necessary, to lubricate the sealing gasket of the head of the soothing bolt with a thin layer of oil-resistant sealant KLT-75;

c) check that there is no plaque on the inner surfaces of the glass that impedes the visual control of the oil level, mechanical damage in the form of cracks and chips; clean the "breathing" hole in the upper cover of the oil indicator with a soft wire;

d) blow out the oil indicators with compressed air at a pressure of no more than 2 kg / cm 2 to check the passability of the oil indicator with control by the pressure of the air coming out through the "breathing" hole;

If traces of oil drips through the seals of the oil indicator, deposits on the inner surface of the glass that impede visual inspection of the oil level, foreign particles (residues of sealant, etc.) or other defects are found, the oil indicator is completely disassembled and the defects are eliminated with subsequent assembly. The damping bolt is then screwed into place last, after the glass sealant has hardened. After assembly, the oil indicator is installed on the oil bath with the inspection hole of the low indicator housing in the direction opposite to the electric motor housing, after which the oil indicator is checked again according to item d).

When installing the bottom half of the upper part of the body and connecting bridges between the bottom bars, use a sealant (paint) as a locking measure in the threaded connection of the bars.

3.13 Technological map of the current repair of asynchronous electric motors 6kV (NR).

Name of operations

NTD (drawings etc.)

Control operations

Fixtures, tools, equipment

Possible defects, malfunctions

Note

Criteria

3.13.1 Disassembly of the electric motor.

Remove the stator terminal cover, disconnect the power cable, ground

IAEG.528122.002 TO

Clean surface of terminals, Integrity of insulators and thread of studs, tight fit of lugs on cables

Oxidation of terminal surfaces, cracking of insulators, thread stripping on pins, loss of fastening of lugs on cables

Grind the surface of the terminals, rinse with gasoline, if necessary replace the insulators, solder the tips

Remove the shroud and cooler fan

IAEG.528122.002 TO

hot-smoked 14х17, center punch, sledgehammer 3kg, assembly crowbar

Remove outer bearing caps (flanges)

IAEG.528122.002 TO

3.13.2 Revision of the stator.

Remove dust, dirt, oil and inspect the stator winding frontal parts

IAEG.528122.002 TO

Contamination-free, tight banding and spacer fit

Bandage needle, bandage tape

Loose bands and struts

Re-band the winding ends, install spacers

3.13.3 Inspection of bearings.

Remove old grease

IAEG.528122.002 TO

Parts washing bath, gasoline B-70

Inspect the bearing

IAEG.528122.002 TO

No visible defects

Holes, chipping, wear marks, matt tracks on rolling surfaces, deformation of balls or rollers

Replace bearing

If replacement is necessary, issue a Fault Detection Report

3.13.4 Revision of the cooler.

Remove dirt and blow dry air from the coolant tubes

IAEG.528122.002 TO

Air blower, lint-free rags, cleaning rod

3.13.5 Assembling the electric motor.

Install both shields on the motor

IAEG.528122.002 TO

Crane-beam, stands, torque gauge 17x19, center punch, sledgehammer 3kg.

Install the outer bearing caps

IAEG.528122.002 TO

Install the cooler fan and shroud.

IAEG.528122.002 TO

Connect the power cable, ground. Close the cover of the stator terminal box,

IAEG.528122.002 TO

Clean lead surface, integrity of insulators and stud threads, tight fit of cable lugs

hot-smoked 14х17, sandpaper, gasoline, soldering iron

Oxidation of terminal surfaces, cracking of insulators, thread stripping on pins, loss of fastening of lugs on cables

Clean the surface of the terminals, rinse with gasoline, if necessary replace the insulators, solder the tips

3.14 Flow chart of current repair of the backup exciter DAZ-18-10-6 (U3), GSP-2000-1000.

Name of operations

NTD (drawings etc.)

Control operations

Fixtures, tools, equipment

Possible defects, malfunctions

Note

Criteria

3.14.1 Disassembly of the exciter.

Remove cable covers and disconnect power cables

Clean surface

hot-smoked 17х19, glass paper

Oxidation of leads

Grind the surfaces of the terminals, rinse with gasoline

Disconnect the cables of the bearing temperature sensors

6BS. 345.030.036

Clean surface

hot-smoked 17х19, glass paper

Oxidation of leads

Grind the surfaces of the terminals, rinse with gasoline

Disconnect the cables from the generator control panel

1BS. 217.038.039

Clean surface

hot-smoked 17х19, glass paper

Oxidation of leads

Grind the surfaces of the terminals, rinse with gasoline

3.14.2 Inspection of the generator stator.

Inspect stator leads

Clean tip surface, No tears or cracks in the insulation

Glass paper, fiberglass, electrical tape

Oxidation of tips, damage to insulation

Grinding, tinning of tips, insulating leads

Tighten threaded connections

VK, test tightening

Tight tightening of threaded connections

Set of wrenches

Loosening of threaded connections

Tighten loose screw connections

3.14.3 Assembling the exciter.

Connect the cables to the generator control panel

1BS. 217.038.039

Clean surface

hot-smoked set, glass paper

Oxidation of leads

Connect the cables of the bearing temperature sensors

6BS. 345.030.036

Clean surface

hot-smoked set, glass paper

Oxidation of leads

Clean the surfaces of the terminals, rinse with gasoline

Install the cable covers and connect the power cables

Clean surface

hot-smoked set, glass paper

Oxidation of leads

Clean the surfaces of the terminals, rinse with gasoline

When replacing a bearing, it must be pressed off the shaft using a screw puller. The new bearing is washed from conservation grease in B-70 gasoline. Heat the bearing in an oil bath or inductor to a temperature of 90 ° C and press it onto the shaft. Bearing installation recommendations are given in Appendix 20. The shaft fits snugly. Then the bearing is filled with grease (LITOL-24, SVEM, TsIATIM-201). After assembly, make a control measurement of the motor insulation resistance and absorption coefficient with a 2500V megohmmeter. The insulation resistance must be at least 40MΩ, the absorption coefficient must be at least the value specified in clause 1.3.2.

I offer an example of a flow chart for the current repair of 0.4 kV asynchronous electric motors with a power of 0.5 - 1.5 kW.

Security measures.

The electric motor must be de-energized, disconnected AB, installed grounding, posted posters. Apply portable grounding to the lead-in ends of the motor cable. Protect the place of work. Work with PPE. Work with verified devices and tested power tools and devices.

The composition of the brigade.

Electrician for the repair of electrical equipment with at least 3 gr. on electrical safety. Electrician for the repair of electrical equipment with 3 gr. on electrical safety.

Tool.

Spanners 6 - 32 mm - 1 set.

Files - 1 set.

Head set - 1 set.

Metal brush - 1 pc.

Plumber's knife - 1 pc.

Screwdriver set - 1 set.

Bench screwdriver - 1 pc.

Dies 4 - 16 mm - 1 set.

Taps 4 - 16 mm - 1 set.

Drill set 3 - 16 mm - 1 set.

Crowbar - 1 pc.

Pliers - 1 pc.

Chisel - 1 pc.

Drill - 1 pc.

Kern - 1 pc.

Flat brush - 2 pcs.

Hammer - 1 pc.

Shovel - 1 pc.

Broom brush - 1 pc.

Devices, devices, mechanisms, protective equipment.

Microohmmeter - 1 pc.

Megohmmeter 500 V -1 pc.

Micrometric level - 1 pc.

Soldering tool - 1 pc.

A set of probes - 1 set.

Vernier caliper - 1 pc.

Safety helmets - individually.

Voltage indicator (380v).

First aid kit - 1 pc.

Mittens - 2 pairs.

Safety glasses - 2 pcs.

Materials and spare parts.

Solder POS - 0.02 kg

Copper-phosphorus solder - 0.02 kg

Alcohol - 0.05 kg

Sealant - oil resistant gasket - 50 ml

Glass tape - 0.150 kg

Electrical insulating varnish - 0.4 kg

Emery paper - 0.5 m

Cleaning materials - 0.5 kg

PVC tape - 0.05 kg

Rosin - 0.005 kg

Kiper tape - 0.5 m

CIATIM grease - 221 - 0.3 kg

White spirit - 0.3 l

Sequence of operations.

P / p No.Name and content of worksEquipment and fixturesTechnical requirements
1 External inspection of an electrical machine, including systems
control, protection, ventilation and cooling.
Compliance with technical data sheets for operation and electrical circuits.
2 Visual check of the condition of the grounding conductor;
checking the condition of the ground loop.
Hammer, shovelLack of anti-corrosion coating, loosening of fastening, mechanical damage are not allowed.
3 Check for extraneous noise. Extraneous noise is not allowed.
4 Cleaning accessible parts from dirt and dust.White spirit, rags, metal brush, broom brush.
5 Inspection of the elements of the connection between the engine and the driven mechanism. Cracks at the seams, breaks, distortions, loosening of threaded connections are not allowed.
6 Checking the connection and tightness of the supplied
cables, technical condition and tightness of lead-in boxes and
sealed bushing couplings;
checking the condition of seals, surfaces and parts that ensure explosion protection;
explosion proof of cable and wire entries.
A set of locksmith probes No. 1 A set of tools a set of screwdrivers A set of heads.Roughness of the working surface Rd no more than 1.25 microns.
7 Checking the fastening of the electric drive to the frame (valve).Set of tools. Set of heads.Loosening of the fastening is not allowed.
8 Inspection of the state of the start-up control equipment (PRA).
9 Blowing out the stator and rotor with compressed air.Compressor.
10 Insulation resistance test of windings;
drying if necessary.
Megohmmeter with a voltage of 500V.Insulation resistance should not be less than 0.5 MΩ.
11 Checking the mating of parts that ensure tightness.A set of locksmith probes No. 1. A set of tools, a set of screwdrivers. Set of heads, sealant.The clearances are indicated in the instruction manual.
12 Checking the presence of grease in the bearings of the electric motor (if there is a press oiler, replenishment).CIATIM-221 grease, grease press-in gun.
13 Inspection, cleaning and tightening of contact connections.Set of tools. Cloth abrasive paper in accordance with GOST 5009-82.Distortions, the presence of oxide, loosening of contact connections are not allowed.
14 Revision of automatic circuit breaker assemblies.Set of tools. Screwdriwer set.
15 Checking the presence of cable markings, inscriptions and markings on the casing, restoration if necessary.Brush, paint (plate).The absence of markings and inscriptions is not allowed.

Additionally, it is possible to indicate in the table the labor intensity, labor costs, and other necessary information applicable to your conditions.