Technological maps of installation of ventilation and air conditioning systems. Typical technological card (TTK) Installation of cooling systems. Installation of split systems, fancoings and chillers Technological card for the manufacture of VENT boxes

Download Document

ROUTING
On the installation of ventilation
Korobov


143-06 TK

First Deputy
General Director

Chief Engineer

A.V. Kolobov

Laboratory boss


B.I. Bychkovsky

A technological map for the installation of ventilation boxes is an integral part of the PPR and is intended for production personnel and engineering and technical workers of construction organizations, works, masters and brigadiers, as well as technicians of technical supervisor associated with these works.

The technological map shows: general data, technology and organization of work, requirements for quality and acceptance of work, labor cost calculation, work schedule, the need for mechanization and tools, solutions for the safety and protection of environmental and fire safety.


Employees of OJSC PactrromStroy participated in the development of a technological map:

Savina O.A. - development of a technological card, computer processing and graphics;

Black V.V. - general technological support;

Bychkovsky B.I. - development of a technological map, technical guide, proofreading and normocontrol;

Kolobov A.V. - general technical guide to the development of technological maps;


K.T.N. Edichka S.Yu. - General management of the development of technological documentation.

1 General Data

1.1 This technological card was developed on the installation of ventilation boxes in industrial, administrative and public and residential buildings.


1.2 Technological map is an integral part of the PPR and is intended for engineering and technical personnel (foreheads, masters) and workers' construction organizations employed on the installation of ventilation boxes, customer technicians who carry out supervisory functions for technology and quality of work, as well as engineering and technical workers Construction organizations.

1.3 Binding a technological map to specific objects and conditions of construction is to specify the scope of work, means of mechanization, the need for labor and material and technical resources, as well as the correction of the calculation and the calendar plan for the production of work.

1.4 The form of using a technological map provides for its appeal in the field of information technologies with the inclusion in the database on the technology and the organization of the construction production of the automated workplace of the construction production technologist (ART TSP), contractor and customer.

2 Organization and technology for performing work

2.1 To install ventilation systems in industrial, administrative and residential buildings, ventilation boxes are used, which can be manufactured from various materials, depending on the medium transported through the air ducts. Table 1 shows examples of materials from which air ducts can be manufactured.


Table 1 - materials for air ducts

Characteristics of the transported environment

Products and materials

Air with a temperature of no more than 80 ° C with relative humidity no more than 60%

Concrete, reinforced concrete and gypsum ventilation blocks, asbestos-cement pipes and boxes, drywall, gypsum concrete and arbolic box; steel thin galvanized steel; Roofing steel, sheet steel; Steel rolled cold rolled; Fiberglass, paper and cardboard; Other materials that meet the requirements of the specified environment

The same, with relative humidity of air more than 60%

Concrete and reinforced concrete ventilation blocks, asbestos cement pipes and boxes; steel thin galvanized steel; steel sheet; aluminum sheet, plastic pipes and plates, fiberglass; paper and cardboard with appropriate impregnation; Other materials that meet the requirements of the specified environment

Air mixture with chemically active gases, pairs and dust

Ceramic and asbestos cement pipes and boxes; Plastic pipes and boxes; Blocks made of acid-resistant concrete and plastibetone; metalplastic; steel sheet; fiberglass; paper and cardboard with the corresponding transportable coatings and impregnation; Other materials that meet the requirements of the specified environment

Notes:

1 Air ducts from asbestos-cement structures are not allowed to be used in ventilation systems.

2 Ducts made of steel sheet cold rolled and hot rolled should have a coating, resistant to the transported medium.

2.2 The external dimensions of the cross section of metal air ducts of the rectangular section should be taken along table 2.

table 2 - external dimensions of metal air ducts


Air ducts rectangular cross section, mm

Note - Dimensions of air ducts from other materials should be specified according to manufacturers.

2.3 The thickness of sheet steel for air ducts, by which air moves with a temperature not higher than 80 ° C, should be taken, not more than:

For rectangular air ducts, size, mm:


from 100? 150 to 250? 250 - 0.5 mm;

from 300? 150 to 600? 1000 - 0.7 mm,

from 1000? 1250 to 1600? 2000 - 0.9 mm,

For air ducts of rectangular sections having one of the sides more than 2000 mm, and the air ducts section 2000? 2000 mm steel thickness should be specified in the project.

2.4 The network of air ducts is composed of unified parts - direct sections, taps, transitions, plugs and branch assemblies from unified parts in accordance with VN 353-86.

For air ducts of rectangular section, straight sections are used with a length of 2500 mm, but the length of the straight section is allowed by constructive and technological considerations.

For the manufacture of air ducts, steel Tonalistic hot-rolled steel according to GOST 19903-74 * and GOST 16523-97, steel sheet and rolled cold-rolled steel according to GOST 19904-90 and GOST 16523-97, steel roofing sheet according to GOST 19904-90.

The air ducts made of thin-grained roofing steel with a size of most side up to 2000 mm should be used straightforward on folds or straightforward on welding, and air ducts having the size of the side of more than 2000 mm, - panel (welded, cylinders).

Air ducts from metal plants should be made on folds, and from stainless steel, titanium, as well as from sheet aluminum and its alloys - on folds or on welding.

2.5 Air ducts depending on the range of transportation is recommended to be transported:

Up to 300 km - by road;

More than 300 km - rail or water.

When transporting air ducts by road, use:

On-board general-purpose cars (GAZ-52-04, GAZ-53A; ZIL-130-76; Ural-377n, KAMAZ-5320, MAZ-5335);

Truck tractors (GAZ-52-04; ZIL-130V1-76; KAMAZ-5410);

Trailers (GKB-817, GKB-8350);

Semi-trailers (CKB-A402; ODAZ-885; ODAZ-9370).

Transport the air ducts by rail should be in the semi-frequencies, the wagons of the closed type should be used in exceptional cases.

2.6 When transporting air ducts, depending on their species and dimensions, it is necessary to envisage.

For ducts of small sections - containing or packing;

For ducts of large sections - telescopic laying;

For semi-finished products - special packaging.

The size and mass of containers and packages must correspond to the dimensions and carrying capacity of vehicles. Table 3 shows the characteristics of containers for transporting air ducts.

Table 3. - Characteristics of containers for transportation of air ducts and ventilation

Container type

Own a lot of container, kg

Gabritis, mm.

The average number of air ducts

Calcoder's organization

Foldable Foldable Container Container KO-1,75A

Trust Soyuzorgsanthmontazh

Container for air ducts STD 523 m

PKB Trust Santechdal

Container for transportation of air ducts NOZ-5

Trust Promveventilation

Air ducts must be installed on a vertically vertically, if they do not go beyond the limits of the dimensions installed for vehicles, and the dimensions established by the Ministry of Transport of Russia.

2.7 As a mechanized lifting facility at objects, winchs, forklift trucks, truck cranes, booms on a pneumocole and tracked run, tower and gantry cranes should be used.

The load-lifting means are selected depending on the mass and dimensions of the venetian equipment and products, the height of their lifting and local conditions.

The area of \u200b\u200bapplication of the lifting tools is shown in Table 4.

Table 4. - Scope of load-lifting mechanisms, mounting steps and scaffolding

Type of lifting mechanism

Operated operations

Characteristics of mechanisms

Mechanisms traction assembly

Vertical (high to 3 m) and horizontal movement of air ducts and ventilations within the working area

With a traction force of up to 16 kN when installing air ducts and light ventilation. With a traction force up to 32 kN when installing ventilation.

Manual mounting winches

Vertical (high to 8 m) and horizontal movement of air ducts and ventilation within the working area

With a traction force of 5 and 12.5 kN when installing air ducts and light ventilation. With traction force up to 50 kN - when installing ventilation

Electric winches

Vertical (height more than 8 m) and horizontal movement of air ducts and ventilations within the working area

With a traction force of up to 10 kN when installing air ducts and light ventilation, with a traction force of 32 kN when installing ventilation

Forklift, equipped with fork picking

Loading and unloading and transportation work on the construction site. Lifting and transportation work on the installation of ventilation

4091, 4092, 4055m, 4013, 4014

Car cranes

Loading and unloading on a construction site and warehouses. Lifting and transportation work when installing air ducts and ventilation at objects

Cranes MCA-6.3 with a carrying capacity of 6.3 tons; MCA-10M carrying capacity of 10 tons; KS-3571 with a carrying capacity of 10 tons; MCA-16 with a carrying capacity of 16 t and others.

Arrow Mounting Crane on Pneumocoles

Crane MKP-16 with a loading capacity of 16 tts and others.

Rift mounting cranes on a tracked go

Loading and unloading on the construction site. Lifting and transportation work when installing air ducts and ventilation at objects

Cranes MKG-6.3 with a carrying capacity of 6.3 tons; Μg-10 with a lifting capacity of 10 tons; Μg-16 with a loading capacity of 16 tts and others.

Tower cranes

Loading and unloading and transportation work on the construction site. Lifting and transport work when installing air ducts and ventilation

Tower cranes used by the general contractor at the construction site

Gantry cranes

Loading and unloading and transportation work on the construction site. Lifting and transportation works on the site of the integuctive assembly and when installing air ducts and ventilation

Gantry cranes used by the general contractor at the construction site

Hydraulic automotive lifts

Lifting and lowering the fans for mounting air ducts and some types of ventilation at the marks above or below the site level on which the hydraulic lifter is installed

AGP-12A, AGP-18, AGP-22 and AGP-28

Self-propelled retractable scaffolding

Lifting of footage-ventilations for mounting air ducts and certain types of ventilation at an altitude of more than 3 m. Lifting and transportation work when installing air ducts and ventilation

Hydraulic telescopic lift

Lifting of locksmith-ventilation plants for installation of air ducts and certain types of ventilation

2.8 The sling of ventilation boxes should be carried out inventory shipping means. The slings are selected depending on the type, the mass of the lifted cargo and the sling method according to Table 5, the main lines are shown in Figure 1.

One of the options for the sling of the air ducts of the rectangular section is shown in Figure 2.

A duct nodes 12 m long and more when the horizontal position is lifted, as a rule, rare parallel pins or traverses. The plumbing of the air ducts should be produced so that they can be submitted to the place of installation in the position closest to the project.

Table 5. - Types of Lines

a - lightweight sling with loops; b - lightweight sling with hooks; in - four-letter sling

Picture 1 - Slings

Figure 2. - Option of the lines of the air duct

When lifting air ducts it is necessary to ensure their stability in a suspended position. The location of the cargo suspension should be located above the center of gravity.

The lifting cargo should be kept from rotation of the pegs from the hemp ropes with a diameter of 20 - 25 mm or dehablings of steel ropes with a diameter of 8 - 12 mm. For horizontal enlarged duct nodes, two dehydrations should be used, for vertical air ducts - one.

2.9 Typical schemes of installation and fastening of winches and tap blocks are shown in Figures 3 - 5.


a) for a column of the building; b) for a brick wall

Figure 3. - Fastening winches


The winches used to move the cargo should be loaded by ballast, the mass of which should not less than twice the traction force of the winch. Ballast should be fixed on the frame of the winch. The designs for which winch and tap blocks are attached must be calculated on additional load.

a - scheme of the location of the tap block in front of the winch; b - fastening of the tap block to ankura;
in - fastening the block to the console; 1 - block; 2 - sling from steel rope; 3 - console;
4 - Inventory Metal Lining

Figure 4. - Installation of the tap block

Figure 5. - Installation of drum winch

2.10 For the entire installation period, the aircraft storage should be equipped.

The device of the attribute warehouse of air ducts must satisfy the following basic requirements:

Located near access roads or railway tracks;

The borders of the warehouse must defend the road at least 1 m;

Be at the minimum distance from the installation object if possible in the zone of the tower crane;

Do not interfere with the production of construction and installation work;

The storage platforms for air ducts must be carefully planned with a slope of 1 - 2 ° for removal of surface waters, covered with drainage sand or gravel, and in the necessary cases - have cuvettes;

Passages, passages and loading and unloading sites must be cleaned of garbage, construction waste (in winter - from snow and ice) and sprinkled with sand, slag or ash;

Storage of ventilators should be organized in compliance with the security requirements of work and fire protection;

In the corners of the open warehouse, barrier poles must be installed, warning signs are posted for motor transport drivers and pointers with the name of the assembly control or the site and the location of the cargo acceptance;

The warehouse should be lit.

2.11 The storage and storage of air ducts should be organized in accordance with current standards and in compliance with the following requirements:

Rectangular air ducts should be laid in the stack; Straight areas height not more than 2.7, fittings - no more than 2 m;

Ducts of the circular section should be installed vertically;

Air ducts delivered in inventory containers should be stored in these containers on specially organized container sites. Store ducts and other products in railway containers are prohibited;

Each duct during storage should be laid on wooden inventory lining;

Air ducts in stacks should be placed taking into account the installation sequence: stacks and containers - provide pointers;

There should be passes with a width of at least 1 m between stacks; Every three stacks should arrange passages for transport with a width of 3 m.

Moving air ducts to overlap multi-storey buildings is carried out using lifting and transport equipment or manual transport.

2.13 Before starting the installation of ventilation systems, the General Contractor must be performed:

Installation of intergenerational floors, walls and partitions;

Device of foundations, bases or sites for installing fans, air conditioners and other ventilation equipment;

Building structures of ventilation chambers of the supply systems;

Waterproofing work in places of installation of air conditioners, intake ventilation chambers, wet filters;

The device of floors (or appropriate preparation) in the installation places of fans on spring vibration insulators, as well as "floating" bases for installing ventilation equipment;

Device support for the installation of roof fans, exhaust mines and deflectors on the coatings of buildings;

Holes are prepared in the walls, partitions, overlaps and coatings necessary for laying air ducts;

Applied on the inner and outer walls of all rooms auxiliary marks equal to the design marks of pure floor plus 500 mm;

Plastered (or lined) surfaces of walls and niches in places of air ducts;

Mounting openings were prepared in walls and overlaps to supply large-sized equipment and air ducts and mounted crane beams in ventilation chambers;

Installed in accordance with the working documentation mortgage parts in building structures for fastening equipment and air ducts;

The possibility of including power tools, as well as electrical welding machines at a distance of no more than 50 m one from the other;

Glazed window openings in outdoor fences, inlets and holes are insulated;

Made activities that ensure safe production of installation work.

An acceptance of an object for installation should be carried out by employees of the production preparation site together with engineering and technical workers of the assembly organization with the compilation of the act.

2.14 Method of installation of air ducts is chosen depending on their position (horizontal, vertical), placement relative to the designs (inside or outside the building, in the wall, in the columns, in the interfer space, in the mine, on the roof of the building) and the nature of the building (single or multi-storey , industrial, public, etc.).

2.15 Installation of metal air ducts is carried out in the following technological sequence:

Marking places of installation of air duct fixtures;

Installation of fastening agents;

Coordination with builders of location locations and methods for fastening lifting facilities;

Installation of lifting facilities;

Delivery to the place of installation of duct details;

Checking the completeness and quality of the delivered parts of the air ducts;

Assembly of parts of air ducts in enlarged blocks;

Installing a block into a design position and consolidation of it;

Installing the plugs on the upper ends of vertical air ducts located at an altitude of up to 1.5 m from the floor.

2.16 For connecting rectangular ventilation boxes, flange compounds and robes are usually used. Rectangular flanges are made of size 100? 150 - 1600? 2000 mm.

The design of the flawless cutting compound of the air ducts of the rectangular section is shown in Figure 6.

The assembly of the air ducts in the integrated blocks with the help of the roll connection is made at pre-installed rubber gaskets in the tire stream, as can be seen in Figure 6a. Combining tires among themselves and ensuring the alignment of the air ducts is performed by the mandrel inserted into the hole of the mounting squares. Then the tires on one side are tightened with fixative ticks and on them for a length of 10 - 15 mm they have a rail, after which the hammer blows through the wooden laying, the rail is scored for the entire length. Connecting rails are installed first on the vertical sides of the air ducts, and then horizontal. This ensures a dense pressing of rubber gaskets among themselves and the tightness of the compound.

When installing the rails on the bersed ends of the air ducts, the profiled rubber gasket is set between the ends, as shown in Figure 6b, after which the air ducts are connected by the slats scored with light blowing blows.

When connecting rectangular air ducts using Z- and C-shaped rails (without the use of rubber gaskets), in order to seal the joint, the outside should be missed by the thickness of the paint or preheated to 50 ° with the "Butaprol" mastic, as shown in Figure 6B.


a - with the use of tires; b - with the use of rails on the beaded ends of the air ducts;
B - with z- and C-shaped rails; 1 - air duct; 2 - connecting rail;
3 - rubber sealing gasket T-shaped; 4 - dense paint

Figure 6. - Babertrase coat compounds of rectangular air ducts


2.17 The maximum length of the enlarged blocks of rectangular air ducts mounted horizontally and connected on tires and rails depends on the capture location scheme and is 6-12 meters. In the case of the use of special traverses, block length can be increased to 15 m, depending on the traverse design. Vertical air ducts are mounted by enlarged blocks within 1 - 2 floors of the building.

2.18 The length of the block is determined by the size of the section and the type of air duct connections, installation conditions and the presence of lifting facilities.

The length of the enlarged blocks of horizontal; The air ducts connected on the flanges should not exceed 20 m.

The schemes of the working area in the installation of air ducts in industrial buildings and structures are given in Figures 7 - 13.

1 - Containers for air ducts; 2 - assembly tables; 3 - lifting rolling

Figure 7. - scheme of organization of work when installing air ducts lifting

rolling in blocks of coating on the conveyor

1 - Console with block; 2 - winch; 3 - autoogidpex; 4 - traverse; 5 - delay; 6 - Block

Figure 8. - Scheme of the organization of the working area when installing air ducts on the outer wall of the building


1 - winch; 2 - traverse; 3 - enlarged duct assembly; 4 - suspension

Figure 9. - scheme of the organization of the working area when installing horizontal air ducts in the building

1 - enlarged duct assembly; 2 - traverse; 3 - truck crane; 4 - autohydrovant

Figure 10. - Scheme of the organization of the working area when installing horizontal air ducts on the overpass


1 - enlarged duct assembly; 2 - semi-automatic sling; 3 - winch 4 - block; 5 - console; 6 - brackets; 7 - stretch

Figure 11. - Scheme of the organization of the working area when installing vertical air ducts on the outer wall of the building

Figure 12. - scheme of the organization of the working area when installing vertical air ducts in the building by the method of "build-up bottom"

1 - air duct; 2 - mast; 3 - assembly traction mechanism; 4 - stretching; 5 - thrust;
6 - hinge; 7 - Stand; 8 - clamp; 9 - inventory sling; 10 - Podcasts

Figure 13. - scheme of the organization of the assembly zone when installing vertical air ducts

2.19 Air ducts must be mounted regardless of the presence of technological equipment in accordance with the design bindings and marks. The addition of air ducts to technological equipment should be made after its installation.

When installing the air ducts, it is necessary to withstand the standard mounting distances in the places of complex intersections of air ducts and other communications and layouts of air ducts in the mine, as shown in Figures 14 - 16.

With sizes b and b 1 from 100 to 500? \u003d 100 mm

»» From 600 to 1600? \u003d 300 mm

Figure 14. - minimum mounting distances from building structures to air ducts

Figure 15. - Minimum mounting distances from engineering communications to air ducts

D Д?, B 1 and b? 1 - diameters and side of respectively round and rectangular ducts

Figure 16. - minimum mounting distances between air ducts

Air ducts in mines, niches, etc. It is necessary to place in such a way that they are conveniently mounted and servicing.

2.20 Fastening horizontal metallic uninsulated air ducts (clamps, suspension, supports, etc.) on the inflaming compound should be installed at a distance of not more than 4 m from the other with the size of the larger side of the rectangular duct less than 400 mm and at a distance of no more than 3 m from the other - with the size of the most side of the air duct of the rectangular section of 400 mm or more.

Fastening horizontal metal uninsulated air ducts on the flange connection of the rectangular section in the sizes of its main side to 2000 mm are inclusively installed at a distance of no more than 6 m from the other distance between the fasteners of isolated metal air ducts of any size of cross-sections, as well as uninsulated rectangular air ducts with the size of it greater Parties more than 2000 mm are assigned to working documentation.

Clamps should cover metal ducts tightly.

Mounting vertical metal air ducts are installed at a distance of not more than 4 m one from the other.

Drawings of non-type fasteners should be included in the working documentation.

The fastening of vertical metal air ducts inside the premises of multi-storey buildings from the height of the floor to 4 m are performed in the interleaved floors.

The mounting of vertical metal air ducts indoors with the floor height of more than 4 m on the roof of the building is assigned to the project (work project).

The attachment of stretch marks and suspensions directly to the flanges of the air duct is not allowed. The tension of adjustable suspensions should be uniform.

Freely suspended ducts must be swallowed by installing double suspensions every two single suspension at a suspension length from 0.5 to 1.5 m.

With the length of the suspension of more than 1.5 m, double pendants are installed through each single suspension.

2.21 When mounting vertical ventilation boxes in a residential multi-storey complex before the start of work, it is necessary:

Perform work on concreting monolithic sites around the opening of mines on the 1st floor and every three floors with leaving openings under vent. On other floors, instead of monolithic areas, install removable flooring of wooden shields. Laying the shields to produce wooden runs from boards 50? 150 mm in the direction "from ourselves", fixing the shields from the displacement of cross-wing plackets;

Clear from the pins of concrete reinforced concrete walls of the mine;

On each floor, protect the openings with a protective fence with a height of 1.1 m. The racks are fixed for concrete walls using a corner of a corner welded from above and from below to racks parallel to the enclosing concrete walls;

Organize the place of reception of vertical ventilation risers in the basement;

On the last overlap, install and secure the manual winch and the mounting unit with a carrying capacity of 1500 kg;

Perform job coverage and approaches according to GOST 12.1.046-85 on each floor.

Mounting the vertical ventilation box in a residential high-rise building is shown in Figure 17.

Installation options for wincing Ventcourts are shown in Figures 18 and 19.

2.22 Production of work on the installation of vertical ventilation boxes in a residential high-rise complex occurs in the following order:

Collecting in the basement or on the first floor, a duct with a length of 12 m from six sections of 2 m long each, as shown in Figure 20;

Each 12-meter whip climbs up the upper section using the winch and the mounting unit;

The lines of cargo shown in Figure 20 (node \u200b\u200b2) is made by a hook for a loop welded to the pipe installed inside the section. The hook is fixed through the oval link to the cable of the winch;

Figure 17. - Mounting scheme of vertical ventilation boxes in high-rise
residential complex with the help of a winch installed on the overlap and the tap block

a) the winch is installed at the overlap; b) frame under the winch

Figure 18. - first option to install manual winch

After lifting the first leaf, it is fixed by the project on the air duct clamp, as shown in Figure 20 (node \u200b\u200b1). The clamp is fixed in monolithic overlap and flanges are welded to it. Similar mount is made throughout the mine through the floor;

After fixing the shoulder of the project, a rope with a hook is released and lowered through the fixed air duct down to lines the air duct assembled in the basement or on the first floor.

a) the winch is installed above the opening of the mines; b) frame under the winch

Figure 19. - Second option for installing manual winch

The connection of the air duct is made on bolts and on welding.

In the process of assembling every 6 sections, temporary supporting the intermediate section on the corners laid onto the overlapping is performed.

As the screamers lifted the opening of the mine openings on each floor with wooden flooring or professional flooring.

The upper section of the air duct must be asleeping to ventucleobam installed through the opening in the coating (using the method of extension from above).

Figure 20. - Ventkoba Ventkord Assembly Scheme of 6 Sections

3 requirements for quality and acceptance of work

3.1 The quality of work on the installation of ventilation boxes should be carried out by specialists or special services that are part of a construction organization or those attracted from the part, equipped with technical means that ensure the necessary accuracy and completeness of control.

3.2 Quality quality controls are carried out at all stages of the technological chain, ranging from the development of the project and ending with its implementation on an object based on PPR and technological maps. Quality control should include input control of working documentation, structures, products, materials and equipment, operational control of individual installation processes or production operations and assessment of compliance of work performed.

3.3 With the input control of the working documentation, it is checked for its completeness and sufficiency of the technical information contained in it for the work of work.

With input control of products, materials and equipment is checked by an external inspection compliance with their requirements of standards or other regulatory documents and working documentation, as well as the availability and maintenance of passports, certificates and other accompanying documents.

3.4 Air ducts and parts of ventilation systems must be manufactured in accordance with working documentation, installation drawings and approved in the prescribed manner, the technical conditions of TU 36-736-78 "Metal ducts" and TU 36-2581-83 "Air Ducts from Metal Plast".

The permissible deviations of the external dimensions of the transverse sections of the air ducts should not exceed the values \u200b\u200bspecified in Table 6.

Table 6. - Allowable deviations of the external dimensions of the transverse sections of the air ducts

The non-sympathy of the walls of the rectangular air ducts should not exceed the values \u200b\u200bspecified in Table 7.

Table 7. - non-planosity of the walls of the air ducts of a rectangular cross section

3.5 The ends of the direct portions of the air ducts must be perpendicular to their axes or adjacent surfaces. The deviation from the perpendicularity of the end should not exceed 10 mm per 1000 mm length of the side of the cross section of the air duct.

3.6 Angular dimensions of air ducts (taps, branch sites, transitions, etc.) must comply with the requirements of the installation projects. At the same time, the allowable deviation should not exceed ± 1 ° 30?.

3.7 Connecting parts intended for installation of air ducts on flanges and inflating compounds (bandage, robust, etc.) must comply with the requirements of the technical documentation for the connection type approved in the prescribed manner.

3.8 Control of the correctness of the main dimensions of the air ducts should be made according to the approved technology of the manufacturer with the following tool:

Metal line (GOST 427-75 *);

Roulette measuring (GOST 7502-98);

Corolotic of 90 ° (GOST 3749-77 *);

Caller (GOST 166-89 *);

A tilter (GOST 5378-88);

Templates made at the factory.

3.9 Quality of coatings, seams, flanging, fastening of connecting products, fastening parts, hardness elements and tires, exterior products, as well as completeness, marking and packaging are checked visually.

3.10 The package of air ducts should include products indicated in the installation project (samples, sketches), with the exception of dust and regulatory devices - cyclones, dampers and valves (all types), noiselessness, manufactured by appropriate standard drawings and tu and fastening means.

Bandages, rails and other parts provided for by technical documentation for these types of compounds approved in the prescribed manner should be included in the air ducts connected on inflaming compounds.

Each duct kit must be accompanied by an assembly project (statements, sketches, schemes) in one instance and an invoice of the manufacturer with a level of technical control.

3.11 Air Force Products must have labeling signs applied to an inner or outer surface at a distance of 100 - 300 mm from the end of the oil paint product, which differs in color from the main paint.

The results of the input control should be listed in the "Log of input accounting and quality control of the obtained parts, materials, structures and equipment".

3.12 Operational control is carried out directly in the process of performing operations on the installation of ventilation boxes, as well as immediately after completion of the work. During operational control, compliance with the installation of ventilation boxes, compliance of the work performed by working drawings, construction standards, rules and standards should be met. The results of operational control must be recorded in the journal of work.

Operational control should be carried out constantly in the process of manufacturing installation.

Map of operational control of metal air ducts is shown in Table 8.

Table 8. - Map of operational monitoring of metal air ducts

Technological process

Controlled indicators

Measuring tool

Type of control

Delivery of air ducts to the place of installation

Check the completeness of the ventilation system (the presence of control devices, fastening means, etc.)

Permanent 100%. Visually. Compliance with components, sketches

Marking of places of installation of fixture of ducts

Fastening step in accordance with SNiP 3.05.01-85

Roulette L \u003d 10 m

Permanent 100%

Plumb m \u003d 200 g

Drilling holes in building structures

Depth of drilling

Meter steel

Permanent 100%

Installation of fixtures

Strength installation of fasteners

Permanent 100%. Visually

Assembly in the integrated nodes of parts of air ducts, adjusting and air distribution devices on the site

The correct assembly in accordance with the project. Tightness of the connections

Visually. Permanent 100%

Lifting to the design mark and the connection between the enlarged duct units with the preliminary consolidation

The position of transverse seams and detachable compounds of air ducts relative to building structures. Vertical of risers. No fussy, curvature on direct ducts

Plumb m \u003d 200 g

Visually. Permanent 100%

Reconciliation of mounted ducts and final consolidation of them

Horizontality of the installation of air ducts and compliance with the slopes in the separating areas of the air ducts. Density of air duct coverage clamps. Reliability and appearance of fixtures

Metric meter,

roulette l. \u003d 10 m,

level l. \u003d 300 mm

Permanent 100%. Visually

Attaching air ducts to ventilation equipment

Correct installation of soft inserts (no proviscial)

Permanent 100%. Visually

Treading the action of regulatory devices

Smooth operation of regulatory devices

Weekend 100%. Visually

3.13 In assessing the compliance of the work performed, the compliance of the compliance of the assembly work of the requirements of the design and regulatory and technical documentation and the quality assessment of the work should be checked.

3.14 When monitoring the quality of work at individual stages of installation of ventilation boxes, should be checked:

Position of transverse seams and detachable compounds of air ducts relative to building structures;

Vertical of risers;

The absence of fuses, curvature and screw-formation in direct areas of air ducts;

The biases in the separating areas of the air ducts, which are transported by air with high relative humidity;

Carefulness and correctness of the supply of gaskets in flange compounds;

Reliability and appearance of fixtures of air ducts, air distribution devices, umbrellas, local suns (special attention should be addressed to fastening air ducts to be insulated or already isolated);

Correct installation of soft inserts;

Smooth operation of regulatory devices and ease of management of them;

Painting of painting of air ducts and other elements of ventilation systems and matching the type of painting project.

3.15 The deviation of the air ducts from the vertical should not exceed 2 mm per 1 m length of the air duct.

3.16 Air ducts intended for transportation of moistened air should be mounted so that at the bottom of the air ducts there is no longitudinal seams.

Plots of air ducts in which dew drops from transported wet air should be laid with a slope of 0.01 - 0.015 to the side of drainage devices.

3.17 Gaskets between the flanges of air ducts should not appear inside the air ducts.

3.18 Bolts in flange connections must be tightened, all bolt nuts should be located on one side of the flange. When installing bolts vertically, nuts should be located on the bottom side of the connection.

3.19 Work on the installation of ventilation boxes in industrial, administrative and residential buildings should be carried out in accordance with the rules of production and acceptance of work according to:

SNiP 3.05.01-85 internal sanitary systems;

SNiP 12-01-2004 construction organization;

Snip 12-03-2001 Labor safety in construction. Part 1. Common Requirements;

Snip 12-04-2002 Labor safety in construction. Part 2. Construction Production;

Snip 41-01-2003 Heating, ventilation and air conditioning;

PPB 01-03 Fire safety rules in the Russian Federation.

4 Requirements for safety and labor protection,
Environmental and Fire Safety

4.1 Installation of ventilation boxes should be carried out in accordance with the requirements of safety, sanitation and occupational hygiene, established by state standards of the Labor Safety Standards System (SSBT), Construction Conducts and Rules for Labor Safety, approved by the Russian State Supervision, Rules and Rules approved by state supervisory organizations .

4.2 Before ademing to work on the installation of ventilation boxes, managers of organizations are obliged to ensure training and commissioning of labor safety instructions in the workplace in accordance with the requirements of GOST 12.0.004-90.

4.3 The work at the height is allowed by persons not under the age of 18, which have passed a medical examination without contraindications to performing work at altitude, having professional skills that have trained safe methods and techniques and received the appropriate certificate.

To perform independent overlap work in accordance with the list of heavy work and work with harmful or hazardous working conditions, when performing the use of labor of persons younger than eighteen years, persons (workers and engineering and technical workers) are allowed, who have passed medical examination and Recognized to perform overlap works, having experience of overlap work for at least one year and the tariff discharge is not lower than the third.

Employees for the first time admitted to overwhelming work, for one year should work under direct supervision of experienced workers appointed by the order by the organization.

4.4 Persons who have passed the appropriate training, briefing and verifying the knowledge of the rules of safe work in a special journal and having a qualifying certificate are allowed to electric welding works. Persons having medical contraindications are not allowed to electric welding work.

4.5 The work with an electrified tool is allowed by persons not under the age of 18, which have passed a medical examination, trained by the rules for using the tool, safety and having an electrical safety group not lower than II, and to connect and disconnect electrically with a group of not lower than III. The entire electrified tool is subject to accounting and registration in a special journal. On each instance of the tool should be an account number. Observation of the health and timely repair of an electrified tool is assigned to the department of the main mechanic of the construction organization. Before issuing an electrified tool, it is necessary to check its serviceability (the absence of a closure on the body, isolation from the feed wires and handles, the state of the working part of the tool) and its work at idle.

4.6 Responsibility for the right organization of safe work on the facility is assigned to the manufacturer of works and master.

4.7 When performing work on the installation of ventilation boxes, SanPiN 2.2.3.1384-03 "Hygienic requirements for the organization of construction production and construction work should be performed.

4.8 Admission of unauthorized persons, as well as workers in a drunken state on the territory of the construction site, in production, sanitary and household premises are prohibited.

4.9 Installation works of air ducts are manufactured according to the preparation of work in the conditions of dangerous and (or) harmful production factors.

4.10 Installation of ventilation boxes should be conducted only in the presence of a project for the production of works, technological maps or mounting schemes. In the absence of these documents, the installation works are prohibited.

4.11 The procedure for making the installation of ventilation boxes, a specific project manufacturing project, should be such that the previous operation completely eliminates the possibility of industrial danger when executing the following. Installation of air ducts should, as a rule, be carried out by large blocks using lifting mechanisms.

4.12 Under mounted ducts, people should not be. You can not fix the suspended duct or block of air ducts for farms, overlap and other building structures in places not provided for by the work project.

4.13 Installation of air ducts from forests, scaffolding and sites, made in accordance with the requirements of GOST 24258-88, should be carried out at least two workers.

4.14 Combining the holes of the flanges when connecting the air ducts should be made only by mandrels. It is forbidden to check the coincidence of the holes connected by the flanges with your fingers.

4.15 It is not allowed to perform work on the installation of air ducts on the roof of buildings during ice, fog, excluding visibility within the front of the work, thunderstorms and wind speed of 15 m / s or more.

4.16 To prevent rocking or twisting of the raised air duct blocks, it is necessary to use deficule of the hemp rope.

4.17 Installation on the installation of ventilation boxes is allowed to produce only a good tool. Wrench keys must accurately match the sizes of nuts and bolts, not to have knocked out on the edges and burrs on the handle. You should not pinch or clean the nuts with the key of large (compared to the head) size with the lining of metal plates between the edges of the nut and the key, as well as lengthen the wrench by attaching another key or pipe.

4.18 Workplaces and plots of work when installing ventilation boxes in the dark should be covered in accordance with the requirements of GOST 12.1.046-85. The illumination should be uniform, without blinding the lighting devices on the working. The production of works in unlit plases is not allowed.

4.19 Before the start of work on the installation of ventilation boxes, dangerous for work and passage of people should be shred, to provide inscriptions and pointers, set security signs according to GOST R 12 4.026-2001, and when working at night, refer to light signals.

4.20 In work projects, it is necessary to indicate dangerous zones in which harmful factors exceed the maximum permissible concentrations or extremely permissible levels.

4.21 Installation sites should be well lit. General lighting lamps attached to the power supply voltage 127 and 220 V must be installed at a height of at least 2.5 m from the ground level, floor, flooring. With a suspension height of less than 2.5 m, the luminaires must be connected to the voltage network not higher than 42 V.

4.22 When installing air ducts in the work projects, it is necessary to include the installation of fasteners, for which the edge of the air ducts can be gained when working at height.

4.23 Ventilation billets of metal air ducts must be completed complete in accordance with TU 36-736-78, do not have distortions, burrs and other defects that impede installation work and can lead to injuries working with accumulating fans.

4.25 When performing work on the painting of air ducts and their parts, as well as the sealing of air ducts with the use of compounds containing harmful substances, the requirements of POT RM-017-2001 "Inter-sectoral labor protection rules under painting works", as well as GOST 12.3.016 87.

4.26 Operation of building machines (lifting mechanisms, means of small mechanization), including maintenance, should be carried out in accordance with the requirements of SNiP 12-03-2001 and instructions of manufacturers. Operation of load-lifting mechanisms, in addition, should be made with regard to PB 10-382-00 "Rules of device and safe operation of lifting cranes".

4.27 Places of performing electric welding works of open arc must be fenced with the help of non-aggravated shirms, shields, etc.

4.28 In the production of electric welding work in the open air above the installations and welding posts, canopies from non-aggravated materials should be built. In the absence of canopies, electric welding work during rain or snowfall must be discontinued.

4.29 To protect the molten metal drop-down during electric welding and slag at the place of welding in places of people, it is necessary to install a dense platform, covered with sheets of roofing iron or asbestos cardboard.

4.30 When installing ventilation boxes on roofing with a slope of more than 20 °, as well as regardless of the slope on wet and covered with inheree or snow, roofing workers should apply safety belts, as well as ladder widths of at least 0.3 m with transverse straps to stop legs; Draps during operation must be fixed.

4.31 Loading and unloading work should be performed in accordance with GOST 12.3.002-75 *, GOST 12.3.009-76 *.

4.32 Loading and unloading work must be carried out by a mechanized manner with the help of lifting and transport equipment and means of small mechanization. Laying manual manually follows from exceptional cases, observing the rules set by the current documents.

4.33 With loading and unloading of ventilation blanks of air ducts and their parts, containers should be applied. While lifting, lowering and moving the container, the workers cannot be on it or inside it, as well as on a number of containers located.

4.34 The lines and the distribution of goods should be made in accordance with PB 10-382-00.

4.35 Submission of materials, ventilation blanks, equipment on workplaces should be carried out in a technological sequence ensuring safety of work. It is necessary to store the workpieces and equipment in the workplace in such a way as not to be created danger when performing work, passes were not cramped and there would be an opportunity to assemble air ducts into enlarged blocks. It is necessary to monitor the correct placement of equipment and blanks on overlaps, avoiding concentration and not exceeding permissible loads per 1 m 2 overlap.

4.36 Ventilation blanks should be stored in stacks with a height of no more than 2.5 m on gaskets and lining. Large and heavy equipment should be stored in one row on lining.

4.37 The storage area of \u200b\u200bbillets and ventilation equipment at the construction site should be fenced and located in the existing lifting crane area. The placement platform should be planned, have slopes for water drain, and in winter, clean from snow and ice.

4.38 Explosive or harmful paints and other materials are allowed to store on workplaces in quantities that do not exceed replacement needs. Such materials must be stored in a tightly closed container.

4.39 Combustible and flammable liquids (kerosene, gasoline, as well as lubricants and dyes) should be kept in rooms from non-aggravated materials or blown in the ground.

4.40 Between the stacks (racks) on the venues and in warehouses, there should be passes with a width of at least 1 m and travel, the width of which depends on the dimensions of transport and loading and unloading agents serving the warehouse or platform.

4.41 Heads of installation organizations are obliged to provide workers, engineering and technical workers and employees with workwear, footwear and other personal protective equipment in accordance with regulatory requirements.

4.42 All persons on the construction site are required to wear protective helmets. Workers and engineering and technical workers without protective casses and other necessary means of individual protection for the installation of air ducts are not allowed.

4.43 When working at height, installers of ventilation systems should be used by safety belts.

4.44. Workers and employees receiving personal protective equipment (respirators, gas masks, safety belts, helmets, etc.), must be trained by the rules of use.

4.45 All work on the installation of ventilation boxes lead in the presence and under the leadership of the responsible ITR in accordance with the rules of production and acceptance of works according to SNiP 3.05.01-85 with strict observance of labor safety requirements according to:

SNIP 12-01-2004 "Organization of construction";

Snip 12-03-2001 "Labor safety in construction. Part 1. General Provisions ";

Snip 12-04-2002 "Labor safety in construction. Part 2. Construction Production ";

PPB 01-03 "Fire safety rules in the Russian Federation";

Sanpin 2.2.3.1384-03 "Hygienic requirements for organizing construction production and construction work";

SP 12-135-2003 "Labor safety in construction. Industry typical instructions for labor protection.

5 The need for material and technical resources

5.1 To perform installation work on the installation of ventilation boxes, the mechanisms, tools and fixtures are specified in Tables 9 and 10.

Table 9. - statement of hand tools, assembly devices, means of small mechanization and personal protective equipment

Name

Type, Mark, GOST

Technical specifications

Quantity on a brigade of 6 people., Piece.

Grooming steelmaker

Mass, kg 0.5 - 1

Roofing hammer

Mass, kg 1.5

GOST 11042-90.

Sledge hammer blacksmith stupidose

Mass, kg 2 - 4

Chisel cleaned

GOST 11401-75 *

Length, mm 160 - 250

Spanners with open yawn double-sided

GOST 7211-86 *

Several size, mm:

Spanner wrench

GOST 2839-80 *

Several head zoom

10, 12, 13, 14, 17, 19

Wrench wrench separation

Seva size, mm 30

The key of the gas welder is universal

GOST 7275-75 *

Screwdriver Plumbing and Installation (Set)

GOST 17199-88

Length, mm 160 - 250

Combined pliers

GOST 5547-93

Length, mm 160 - 200

Flat Flame Files, Three-edged, Round, semicircular with notch number 1, 2, 3 (set)

GOST 1465-80 *

Length, mm 150 - 400

GOST 7213-72 *

Length, mm 125 - 160

Manual scissors for metal cutting

GOST 7210-75 *

Length, mm 250 - 320

Scriber

GOST 24473-80 *

Length, mm 150

Clamp for assembling a bandage

Maximum zev, mm 150

Handheld frame

GOST 17270-71 *

Castle Length, mm 250 - 300

Pipes for manual drive

GOST 4045-75 *

Scrap mounted

Length, mm 560 - 1320

Steel brush rectangular

TU 494-01-104-76.

Length, mm 310

Brush-mix

Metro Folding Metal

Length, mm 1000

Metal measuring ruler

GOST 427-75 *

Length, mm 500

Metal measuring tape measure

GOST 7502-98.

Tape length, mm 5000 - 20000

Calipers

GOST 166-89 *

Measurement limit 125 mm

Loose-hearter beards

GOST 7214-72 *

Length, mm 160 - 200

Circle Vocket

GOST 24472-80 *

Length, mm 250

An elongated mandrel

Diameter, mm 16

Pliers for assembling a bandage

Maximum zev, mm 120

Construction level

GOST 9416-83

Steel construction removal

GOST 7948-80

Mass, kg 0.4

Injector cutter for manual oxygen cutting

GOST 5191-79 *

GOST 1077-79 *

Gear Plant Processing Reducer

GOST 13861-89

Welder shield

Mounting traction mechanism

MTM-1,6 or

Load capacity, t 1,6

Load capacity, T 3.2

Mounting unit

Load capacity, T 1.25

Mounting unit

Load capacity, t 2.5

Drug Rube

Load capacity, T 3.2

Drug Rube

Load capacity, T 5

Voltage, 380

Three-pole plug

Voltage, in 42

Two-pole plug

Voltage, 250

Drilling machine

IE-1035 or

Drill diameter, mm 14

Drill diameter, mm 23

The diameter of the grinding circle, mm 180

The diameter of the grinding circle, mm 230

Kiyanka flat

Gable, mm 355? 190? 80

Casque construction

GOST 12.4.087-84

Mittens

GOST 12.4.010-75 *

Safety belt for installers

GOST R 50849-96 *

Set of safety signs and labor protection

GOST R 12.4.026-2001

Respirator

"Petal"

GOST 12.4.028-76 *

Table 10. - certificate of hand tools, installation devices and means of small mechanization of periodic needs

Name

Type, Mark, GOST

Technical specifications

Number of 100 workers, pcs.

Electric two-speed drilling machine with electronic rotation frequency control

IE-1204E or IE-1207E

Drill diameter, mm 14/9

Drill diameter, mm 14/9

The same, with electronic rotation frequency regulation

Drill diameter, mm (max.) 9

Electric grinding machine

Grinding circle diameter, mm 125

Electric grinding machine, corner

The diameter of the grinding circle, mm 80

Electric wrench

Thread diameter, mm 12 - 30

Energy hit, J 25

Electric wrench

Thread diameter, mm 16

Tightening torque, n? M 125

Electric screwdriver

Thread diameter, mm 6

Screwdriver with electronic rotation frequency control

IE-3604E or IE-3603E

Thread diameter, mm 6

Thread diameter, mm 6

Electric perforator

Diameter of thread, mm 2

Electric perforator

Thread diameter, mm 2.5

Electric scissors

Thickness of the leaf cut, mm 1

Electric scissors

The thickness of the leaf cut, mm 0.85

Electric scissors

The thickness of the leaf of the sheet, mm 2.5

Electric scissors

The thickness of the leaf cut, mm 1.6

Saw pendulum

The diameter of the abrasive reinforced circle, mm

Electric grinding machine

Circle diameter, mm 100

Electric grinding machine

Circle diameter, mm 100

Fixture assembly for cargo movement

Load capacity, T 1

Hand winch in the installation case

Load capacity, t 0.5

Load capacity, T 1

Load capacity, T 3.2

Mobile compressor

Performance, m / min 0.5

Manual pneumatic sprayer

Paint consumption, l / min 1.6

Hand winch

Load capacity, t 0.5

Hydraulic jack

Load capacity, t 6.3

Balance

Load capacity, kg, up to 12.5

Balance

Load capacity, kg, up to 20

Wedge lining

Load capacity, t 3

Wedge lining

Load capacity, T 5

Wedge lining

Load capacity, t 10

Safety supergrowth device

Maximum mass of falling cargo, kg 100

Montage coil

Mounting unit

Load capacity, T 5

Mounting traction mechanism

Load capacity, T 3.2

5.2 Tables 11 and 12 are the norms of consumption of metal rolling and auxiliary materials per 100 m 2 air ducts and the elements of ventilation systems assigned to them.

Table 11. - Rounds of consumption of metal rolling per 100 m 2 air ducts

Materials

Rolls of consumption of metal rolling 100 m 2 air ducts with ventilation products attributed to them

Black metal rental

Including:

Beams and sewners

Steel Krupolnaya

Medium-standard steel

Mellennaya steel

Tolstolic steel

Steel is a subtlety thickness of more than 1.9 mm

Steel Tonalistic thickness up to 1.8 mm

Black roofing steel

Galvanized steel

Table 12. -Norming of the consumption of auxiliary materials per 100 m 2 duct

Materials

Rounds of consumption of auxiliary materials per 100 m 2 air ducts from roofing and thin-sheet steel (without elements of ventilation systems)

faltsev

Manufacture

Welding materials

Electrodes

Welding wire

Gas carbonate

Painting materials

GF-020 ground

Solvent

Solvent

Mastic "Bupetrol"

Bolts with nuts

Including

Welding materials

Electrodes

Packing materials

Rubber Sheet

Rubber porous

Rubber profiled

Asbestos Corn

6 Technical and Economic Indicators

6.1 Installation of ventilation boxes must perform working relevant qualifications, combined, as a rule, in complex brigades and links. In these brigades for uniform and full loading, workers are encouraged to widely practicing professions.

The composition of the complex brigade on the installation of air ducts, taking into account the possibility of combining professions, is shown in Table 13.

Table 13. - Comprehensive Brigade

The number of workers of this discharge

The total number of workers

Installer of ventilation systems

5 - 6 discharge (brigadier)

Mounting rigging 3 discharge

4 categories

Electric welder 3 discharge

Installer of ventilation systems:

4 categories

3 categories

Mounting rigging 2 discharge

2 categories

Note - Responsible types of welding need to be entrusted to a qualified electric welder.

6.2 As an example of installation of ventilation boxes, we will take the installation of vertical carriages of air ducts of 800? 800 mm with an area of \u200b\u200b100 m 2 with a manual winch.

6.3 Work and machine time costs for the installation of ventilation boxes are calculated on "single standards and rates for construction, assembly and repair work", entered into operation in 1987, and are presented in Table 14.

Table 14. - Calculation of labor costs and machine time to install ventilation boxes

Unit of measurement 100 m 2 ventilation boxes

Justification (Yenir et al. Norms)

Name of technological processes

Scope of work

Rate of time

Labor costs

workers, people -

workers, people -

machineist, Cherts. (work machines, Mash.-B.)

E9-1-46 No. 1A.

Drilling holes with an electric drilling machine in building structures

Table. 3 № 1AB

Delivery to the location of the duct details

Table. 12 № 4V.

Assembling air ducts in enlarged blocks, installation of fastening tools, lifting and installation of blocks, compounding the installed unit with previously mounted, reconciliation and final consolidation of the system

Apply.

Installing plugs on the upper ends of vertical air ducts

6.4Wenergite work on the installation of ventilation boxes is determined by the work schedule of the work presented in Table 15.

6.5 Technical and economic indicators are:

Labor costs, person-hour:

workers: 64,8.

machiter: 0,034.

Duration of work, hour. eighteen


Table 15. - Calendar Plan for the Production of Works

The meter of final products - 100 m 2 ventilation boxes


7 List of regulatory and technical literature

1 SNiP 3.05.01-85 Domestic sanitary systems.

2 SNiP 12-01-2004 Construction Organization.

3 SNiP 12-03-2001 Labor safety in construction. Part 1. Common Requirements.

4 Snip 12-04-2002 Labor safety in construction. Part 2. Construction production.

5 Snip 41-01-2003 Heating, ventilation and air conditioning.

6 GOST 12.0.004-90 SSBT. Organization of learning safety of labor. General.

7 GOST 12.1.046-85 CBST. Building. Norms of lighting construction sites.

8 GOST 12.3.002-75 * PRT. Production processes. General security requirements.

9 GOST 12.3.009-76 * PRT. Works loading and unloading. General security requirements.

10 GOST 12.3.016-87 SSBT. Building. Anticorrosive works. Safety requirements.

11 GOST 12.4.010-75 * PRT. Individual protection means. Special mittens. Technical conditions.

12 GOST 12.4.011-89 SSBT. Means of protecting working. General requirements and classification.

13 GOST R 12.4.026-2001 SSBT. Colors of signal, safety signs and signal markup. Appointment and rules of application. General technical requirements and characteristics. Test methods.

14 GOST 12.4.059-89 SSBT. Building. Fencing safety inventory. General specifications.

15 GOST 12.4.087-84 SSBT. Building. Cooks construction. Technical conditions.

16 GOST 24258-88 Forming means. General specifications.

17 Yenir. Unified norms and rates for construction, assembly and repair and construction work. Collection 1. Domestic transport work.

18 Yenir. Unified norms and rates for construction, assembly and repair and construction work. Collection 10. Construction of ventilation systems, air conditioning, pneumatic transport and aspiration.

19 PB 10-382-00 Rules of device and safe operation of lifting cranes. Gosgortkhnadzor of Russia, M., 2000.

20 PPB 01-03 Fire safety rules in the Russian Federation. EMERCOM of Russia, M., 2003

21 SP 12-135-2003 Labor safety in construction. Industry typical safety instructions.

22 EAS 279-85 Instructions for sealing ventilation and sanitary systems. M., 1985

23 WG 353-86 Design and use of air ducts from unified parts. M., 1986

24 East 470-89 Regulations of the need for manual instrument, installation devices and means of small mechanization for the production of various types of installation and special construction work. M., 1990

25 Manual for the production and acceptance of works when applying ventilation and air conditioning systems (SNiP 3.05.01-85). M., 1989

26 Pot R M-007-98 Labor protection rules for loading and unloading work and cargo location.

27 Pot R M-012-2000 Inter-sectoral rules for labor protection when working at height.

28 Pot R M-016-2001 Intersectoral rules for labor protection (safety rules) during the operation of electrical installations.

29 Pot R M-017-2001 Inter-sectoral rules for labor protection during painting works.

30 Pot R M-020-2001 Inter-sectoral rules for labor protection at electric welding and gas welding works.

Typical Technology Card (TTK)

Installation of cooling systems. Installation of split systems, fancoings and chillers

1 AREA OF USE

The typical technological card is designed to install the cooling systems, split-systems, fancois and chillers.

General

Autonomous air conditioner is an assembly with a built-in refrigeration machine. Such aggregates assume installation directly indoors.

Local air conditioners include split systems consisting of an external block, which includes a compressor-condenser unit, and an internal evaporative unit. The internal unit is installed directly in the air-conditioned room. It is intended for cooling, heating and filtering air, as well as the creation of the necessary mobility of air flow.

The advantages of split-systems include simplicity of design and low labor costs during installation; The disadvantages are circulation without mixing fresh air to the room. Only high-power models allow you to organize a small amount of fresh air (up to 10%).

The external unit can be installed on the wall of the building, on the roof, in the attic, etc., that is, where the heated capacitor can be blown in air to a lower temperature. The indoor unit can be mounted on the wall, on the floor, on the ceiling, behind the suspended ceiling (cassette type), as well as to be decorated in the form of columns-cabinets with dimensions up to 500x800x400 mm.

Wider capabilities have air conditioners split-systems with supply ventilation. Such a system is designed to be installed in places when fresh air is required.

With a significant number of served premises, the application of the system with chillers and fancakes is recommended. Chiller is a refrigeration machine designed to reduce the temperature of the fluid, which under pressure of the pump is supplied to the air conditioner-closer (fancoil) installed indoors. In this case, the air of the room is cooled or heated.

Features of installation of cooling systems of systems

air conditioning (SLE)

General information about the installations of cooling SLE

Among the processes carried out in air conditioners, one of the most important is the process of cooling the air. Refrigerated installations are used to implement this process. Refrigeration facilities are treated as serving SD subsystems that produce "cold".

The most common Hu, working as part of the SC, are compressor refrigeration units. These settings consist of the following main elements: compressor, condenser, thermostatic valve (or capillary tube), evaporatorand pipelines connecting the listed elements into a closed system in which the refrigerant circulates.

Cooling conditioned air occurs in air coolers,which are elements of air conditioners. Find the use of two types of air conditioners air coolers. One of them is a surface recuperative heat exchanger, according to the internal channels of which the intermediate coolant passes, circulating through the evaporator Hu, at some distance from the air conditioner.

Liquids (antifreeze, water, etc.) are used as a coolant. This cooling option is used, for example, in systems with chillers and fancakes. To another type of air coolers of air conditioners, heat exchangers should be attributed, through the internal channels of which the chladone moves (freon), and the outer surfaces of the channels are washed with air. These direct evaporation air coolers are simultaneously elements of refrigeration and air conditioning. They are used in autonomous air conditioners.

Air conditioners air coolers operating on an intermediate coolant receive a cooler, pre-cooled in the evaporator of a refrigeration machine, for example, in a chiller. There is a supply and return pipeline for circulation on them Hu and the air cooler of SCB for circulation. Pipelines must have thermal insulation. Insulation prevents the creation of conditions for condensate falling on the surfaces of cold pipes. Coolant pipelines and their insulation complicate installation work.

So, the discharge systems of the SDC are intended to generate a cold, transmission through the evaporator Hu directly air or transferring the cold with a coolant, transfer of the coolant to the air conditioner's air cooler, the transfer of cold from the cooled air cooled and return the heated cooler to the refrigeration machine to repeat the refrigerator.

There are many varieties of refrigeration systems used in SD. Figure 1 shows the schemes of air cooling systems.

Fig.1. Air cooling systems that determine the conditions for using refrigerants of various pipes

They are presented:

The direct cooling system in which the cooled air is in direct contact with the evaporator Hu;

An indirect cooling system with an intermediate coolant in which Hu evaporator cools the intermediate coolant transmitted then into the air conditioner air cooler, which is in contact with the cooled air.

In indirect cooling systems with an intermediate colaster, five types of execution are distinguished:

An open system with an intermediate coolant and a closed evaporator;

An open system with an intermediate coolant and an evaporator placed in an open-air tank;

A closed system with an intermediate coolant and a closed evaporator, in which the evaporator is in a closed volume, cools the intermediate coolant circulating in this volume, in turn supplied to a closed secondary heat exchanger for cooling air-conditioned air;

The closed system with an intermediate coolant and an open evaporator, the evaporator is placed in the tank, cools the circulating intermediate coolant, in turn supplied to a closed secondary heat exchanger for cooling conditioned air;

Double-circuit or multi-mounted systems with intermediate colasters, which can be performed similarly to one of the listed systems with an intermediate coolant except that there are two or more intermediate heat exchanger in them, and in the last circuit, the intermediate coolant can be directly in contact with the cooling medium in a spray device or similar devices. or similar systems.

Figure 2 shows a diagram of a typical refrigeration unit with an air cooler 1 and air cooling condenser 6 for SLE. The refrigeration unit for SLE, as a rule, consists of two separate blocks: compressor and air cooler compressor and block.

Fig.2. Typical circuit of a refrigeration unit with one air cooler and an air capacitor for SLE:

1 - air cooler; 2 - filter cleaner; 3 - vibration insulator; 4 and 5 - low and high pressure relays; 6 - air capacitor; 7 - Receiver; 8 - filter desiccant; 9 - compressor; 10 - Carter heater; 11 - sight glass; 12 - shut-off valve; 13 and 27 - pressure control relay and condensation; 14 , 15 - body of the solenoid valve with the coil; 16, 17 - thermostatic valve; 18 - regulator of condensation pressure; 19 - Differential check valve; 20 - S1C system; 21 - sight glass; 22 - filter; 23 - Cold launch protection thermostat; 24 - separator liquid; 25 - check valve; 26 - oil separator

Compressor 9 the refrigeration compressor sucks the refrigerant pairs from the evaporator air cooler 1, installed indoors where the required temperature is supported, compresses condensation to pressure and fed to the air capacitor 6 . In the condenser, the steamy refrigerant is condensed, heating air, blowing through it, and the refrigerant goes into a liquid state. From the condenser, the liquid refrigerant enters the receiver 7 . From the receiver enters the filter desiccant 8 where removal of moisture residues, impurities and pollution, then passing through the viewing glass with the moisture indicator 11 , it is throtting in the thermostatic valve to boiling pressure 16, 17 and fed to the evaporator. In the evaporator, the refrigerant boils, removing the heat from the cooling object (air ishing the evaporator).

Couples of refrigerant from the evaporator through a liquid separator 24 and filter on the suction side 2 enters the compressor. Then the cycle of the refrigeration machine is repeated.

2. Organization and technology for performing work

Features of installation subsystems of cooling air conditioning systems (SLE)

Installation of refrigeration equipment is performed according to the project (by a typical or individual project) or a scheme that is attached to the supplied equipment and is described in the factory instructions for installation, operation and maintenance.

When drafting a mounting scheme and an equipment plan, it is necessary to minimize the length of the pipelines of the pipelines.

The sequence of assembly and commissioning works of cooling systems may be as follows:

Installation of refrigeration equipment;

Installation of pipelines and instruments of automation;

Installation of electrical systems;

Testing system pressure on tightness;

System vacuuming;

Refueling system refrigerant;

Starting system;

Adjustment of automation instruments;

Control, registration and output to the operating parameters.

Installation of refrigeration equipmentit is not fundamentally different from the installation of equipment of ventilation systems (SV) and SLE. Specific features of installation are set forth in the technical documentation that enters the object together with the equipment and instruments of the Kipa.

Refrigeration equipment for SLE systems is supplied mainly aggregated - blocks, after installing refrigeration equipment, the connective pipelines are installed: pipelines for refrigerant and pipelines of hydraulic systems. The condition of long-term health of the refrigeration system is the absence of foreign particles, moisture and pollution in the refrigeration circuit. To perform this condition, the refrigerant pipelines are carefully cleaned before assembly. Installation must be performed by professionals that have experience in installing cooling systems. To perform installation work, installers use a special tool set.

Installation of refrigerant pipelines

As a rule, freon pipelines are manufactured from two main types of special copper pipelines designed for refrigeration plants.

1. Pipes with a diameter of up to 7/8 inches (2.2 cm) from annealed copper supplied in bays of various lengths that are well bent with spring frames or pipe bending. They are well collapsed, which allows the use of the pipeline connection. As a rule, kits from dual flexible copper pipes in thermal insulation are used.

2. Pipes with a diameter of more than 7/8 inches from ordinary copper, supplied by segments of not more than 4 m. Such pipes are difficult to bend, therefore the docking of segments and bends of pipelines are performed by special elements (fittings) and are connected using soldering various solders.

For soldering, silver or copper-phosphorous solder are usually used. They have high tensile strength and vibration resistance. Solders are released in the form of a rod 3.2x3.2x500 mm and rods with a diameter of 1.6 mm. Various solders contain from 40 to 56% of silver. For the ideal tube connection, oxygen-containing fluxes are used.

Pipes are placed on the highway in accordance with the project or the mounting scheme and are mainly located horizontally or vertically. The exclusion is the horizontal sections of the suction and injection pipelines, which are performed with a slope of at least (5%) in the direction of the compressor or the condenser to facilitate the return of the oil.

Fig.3. The scheme of installation of oil lubricants on the upstream areas of pipelines is more than 7.5 m:

but- discharge pipe; b.- Suction piping

In the lower parts of the rising vertical sections of suction and discharge triggers, more than 3 m is needed to mount the oil liner. Figure 3 shows the schemes for the installation of oil linked loops on the upstream areas of pipelines with a length of more than 7.5 m, and in Fig. 4 shows the possible design of the oil lining and its recommended dimensions.

Heat insulation work

Calculation, design and installation of thermal insulation is performed by SNIP 41-03-2003 (introduced instead of SNiP 2.04.14-88 * "Heat insulation of equipment and pipelines") and SP 41-103-2000 (calculation method), taking into account the requirements of fire safety, Sanitary and hygienic standards and design standards adopted in certain industries.

In 2003, NTP "Pipeline" (Software) and OJSC "Heat Procective" (settlement techniques and information base) developed a computer program of automated design of thermal insulation of equipment and insulation pipelines. During the insulation of technological pipelines, various types of insulation are used depending on the technical requirements. Progressive types of insulation can be considered insulation based on foam rubber or polyethylene. Each type has its pros and cons. Positive properties of isolation can be reduced to zero with poor quality installation. Leading producers of foam insulation from foamed polyethylene ("Thermaflex International Holding BV", Mirel Trading, Energo Flex) and Synthetic Rubber ("Lisolante K-Flech") "ARMASLL GmbH", "Wihlem Kaimann GmbH & Co" "AERFLECH INTERNATIONAL CO, LTD", "YSOLIS".

When installing isolation, you must adhere to the following rules:

1. Isolation operation is always carried out on cold equipment and pipelines.

2. When cutting and fitting insulating pipes, only high-quality auxiliary tools are used using a professional islerar kit consisting of:

Wooden fixture for cutting and long acute knife;

Templates;

Set of circular stainless knives.

3. Shakes of seams glue with special polychloroprene-based glue at a temperature not lower than 10 ° C.

Fig. 5 and 6 presents the above tools.

Fig.5. Templates

Fig.6. Circular knives

Errors associated with improper insulation installation may result in difficult-scale problems that include:

Arbitrary replacement of insulation marking;

Wrong selection of accessories for installation;

Transition to a smaller thickness of thermal insulation;

Disturbance of the temperature range;

Improper preparation of the system and its surface;

Improper work with glue;

The use of foam insulation to work on the street without additional protection.

Installation of steel pipelines of hydraulic system solid supply SLE

Installation of hydraulic cooling systems of the SLE can be carried out by all industrial methods providing quality compounds in accordance with current regulatory documents. There are three basic methods of connection: welding, connection on the thread and gluing steel pipelines. Compounds weldedsteel pipelines can perform welders if they have documents for testing tests in accordance with the "Rules of Certification of Welders" approved by Gosgortkhnadzor. Welding is made in accordance with GOST 16037-80 "Compounds welded steel pipelines".

Another connection method - compounds on threadwith the help of fittings (shaped parts). The universal set for the installer is presented in Fig. 7.

Fig.7. Universal set for Plumbing Sani Kit in plastic suitcase

The set consists of the following tools:

Pipe cutting pipe cutting diameter to 1 1/4 ";

Fixture for cutting threads with a diameter of up to 1 ";

Plumbing ticks;

Universal corner key Super S1.

Adhesive compounds are used when installing pipelines made of carbon and low-alloy steel (including those having corrosion-resistant coatings - galvanized, enamel, illuminated, etc.) to 100 mm, operating at an overpressure of up to 1.0 MPa, operating temperature from - 60 to 90 ° C and intended for transportation of various substances to which, with the specified parameters, chemically rack epoxy adhesives or fiberglass on an epoxy basis.

Installation of plastic (polymeric) pipelines of hydraulic fooling systems SLE

Currently, polypropylene pipes and fittings are widely used for the installation of CHW Cooling Systems. The advantages of plastic pipes:

Lack of corrosion;

Long service life;

When freezing the pipe is not destroyed, but increase in diameter and after thawing, the former size is acquired;

Good absorption of hydraulic noise;

Low pressure losses in pipes and fittings;

Low thermal conductivity.

For mounting plastic pipelines, various connecting and fastening parts are used. Main ways to connect pipelines:

Contact welding in fool;

Threaded connection with a metal pipeline;

Connection on free flanges;

Connection with a cape nut.

Installation of RRRS systems requires minimal time and effort. The technology of coupling welding allows you to quickly ensure the durability of the sealed connection. The reliability of welded joints is the highest compared to other methods and is approaching the strength to the pipes themselves, but requires higher qualifications from assembly personnel. After installing the freon contour pipelines and testing for tightness of the leak detectors of various types, the system is vacuuming and refueling the refrigerant system using a refueling station or a manometer collector. Depending on the refrigerant used (single-component or multicomponent), refueling can be produced both gaseous and liquid refrigerant. It is always necessary to adhere to the recommendations for refueling the refrigerant in the installation and operation of the air conditioner attached to the supply of equipment. The optimal amount of refilled freon can be determined by the pressure of suction and discharge or overheating in the evaporator.

Features of the installation of split systems, fancocks and chillers

Features of installation of air conditioners split systems

In practice, the installation of small refrigeration units is divided into standard and non-standard. Under standardit is implied by mounting with the length of the refrigerant's length of up to 5 m, the diameter of the suction line up to 16 mm, the location of the connection and control panel at a distance of up to two meters from the unit, with one air cooler, without a remote capacitor and oil liner and the availability of the necessary power.

Standard installation includes:

Delivery of equipment;

Installing units on the wall on specially prepared brackets;

Punching of one hole for connecting communications;

Running track up to 5 m long without oil liner;

Electrical connections and connections of system pipelines;

Checking system for tightness (pressure and vacuum);

Refreshing chladone;

Commissioning works.

Under non-standardinstallation implies installation with the additional requirements of the customer. For example, installing a remote capacitor, the presence of two and more air coolers, an increase in the total pipeline length is greater than 5 m, laying pipelines through several walls (partitions), laying pipelines in decorative boxes, etc.

The split system consists of two separate blocks that can be installed at a considerable distance from each other. Internal blockinstalled in the air conditioning room, and external block- on the outside of the building. In the installations of this type, axial fans are used so that the unit does not work normally, there should be no obstacles to the air flows, you need to comply with the minimum gaps specified in the instructions for the aggregate. The prevailing direction of the air should not be directed to the installation. In apartments and small offices use wall-type split-systems. With greater cooling capacity in the rooms of a complex shape - cassetteor canalindoors with glass partitions - ceilingin the halls of restaurants and large halls - column. If the number of internal blocks becomes greater than six, and the maximum distances between blocks reaches 100 m, such systems are called multi-meant (zonoral modular) or VRF systems.

The internal unit, if possible, is set closer to the window or the wall overlooking the street to reduce the highway the refrigerant pipelines. The maximum distance should not exceed 15 m. On the path of the air flow supplied to the working area, there should be no high objects of the situation, and the cooled flipping stream should cover the maximum area of \u200b\u200bthe room. As air supply in cassettemodules occur in four directions, it should not be mounted close to the wall, and all communications are located behind the suspended ceiling, as well as from channel systems; Free space should be at least 350 mm. Internal blocks channel systemsmust be mounted not far from the outer wall, as they allow mix to (10-20%) of fresh air. As outdoor ceilingand cassette modulescompleted drainage pumping, we must try to have them close to the sewer pipelines for drainage.

External blockmounted on the outside of the building on the ready-made mounting bracket near the window, so that there is an opportunity without a climbers to carry out service work. The unit should be installed so that it is well blown out the outer air and is protected from direct sunlight.

Installation of the external block should be carried out on a sufficiently durable wall on the finished bracket, designed for weight of 80 kg. The block distance from the system must be at least 10 cm.

When choosing a place to install the indoor unit, the following requirements must be taken into account:

It is impossible to place a block next to heat sources and humidity;

You can not install a block near the doorway;

There should be no obstacles to air blowing out of the indoor unit;

At the installation site of the block, a reliable drainage of condensate (drainage) should be organized;

The installation location must be chosen in such a way that there is no direct (straight) supply of cooled air to people;

The distances from the inner block to the walls, the ceiling and gender must be at least certain values \u200b\u200b(Fig.8).

Fig.8. Mounting position of the internal split system unit

Fastening the inner block of wall or outdoor-ceiling type is carried out using a mounting plate and supplied brackets. The mounting plate is attached to the wall with screws strictly by level. In this case, a normal condensate is provided with an air conditioner when operating.

For condensate drain, a special drainage pipe is installed, usually performed from a soft corrugated tube. Sometimes a rigid smooth tube is used, for example, when laying a drainage pipeline in suspended ceilings with small slopes.

Drain is made in the sewage to the street, and sometimes in a special capacity, as a rule, gravity. If for any reason it is impossible to organize a drop of condensate by gravity, then you need to use drainage pumps. When dragging the drainage through the wall to the street, it is necessary to drill a hole with a slope (outdoor edge below internal).

Stretching copper tubes, control cable and drainage tube through a hole, it is necessary to ensure that there is no breaks, breakthroughs, jams on the drainage tube. It is unacceptable to touch the drainage tube bare, i.e. Unprotected thermal insulation of the gas highway, especially for modules with a thermal pump. When air conditioning in heating mode, the temperature of the gas highway can reach a value sufficient to melting the material from which the drainage tube is made, which can lead to blockage of the drainage system.

The drainage tube must have the necessary bandwidth and laid with a slope of at least 1% in such a way that it does not raises and sagging during the pipe.

It is recommended to remove the condensate into the sewage indoor. Before the seat of the condensate, a siphon must be installed in the sewage system, which prevents the penetration of unpleasant odors to the room.

When the air conditioner is operating in the winter in cooling mode, there is a danger of moisture freezing at the outlet of the drainage pipeline. For the prevention of freezing the output section of the drainage pipeline, special electrical heaters or heating cables of the corresponding power can be used. Their power supply should be made independently of the rest of the electrical circuit and constantly, except for the maintenance of the maintenance of air conditioners.

When installing an internal unit under the ceiling, it is necessary to ensure the possibility of removing the filter for cleaning.

Column-type air conditioners are installed on the floor and can be attached to the wall to give stiffness.

Internal and external blocks are combined with copper tubes in thermal insulation.

FEATURES OF MAINTAGE FENKOILLS

The local air conditioning system used for cooling or heating air, with a built-in fan, filter, electric heater and a control panel is called fancoil. Fancois are produced in various designs:

For vertical installation under the window in the case;

For hidden vertical installation under the window without housing;

For the horizontal installation under the ceiling in the case;

For a hidden horizontal installation in a tail ceiling;

Cassette type for installation in a tail ceiling;

Wall, by analogy with internal blocks of split systems;

Cabinet type.

Fancois are installed by groups serving several rooms or floors. Schemes of pipelines of heat boat supply system can be two-pipe, three-pipe and four-pipe, depending on the tasks that need to be solved. Accommodation and installation are manufactured according to the installation and maintenance instructions that are supplied with fancoil. The installation feature is the correct setting of the hydraulic system using balancing valves to ensure the required distribution of fluid on all fancois.

Features of chiller mounting

Chillerit is a complete refrigeration machine intended for cooling fluid (water, non-freezing liquids). System chiller-fankilit differs from all other air conditioning systems in that there is no freon between the outer and inner blocks, and the water, aqueous solution of propylene glycol, ethylene glycol, or other antifreezes is circulated. Installation is made in accordance with the Chiller Installation Guide, which is supplied by the manufacturer. When placing chiller, pay attention to:

On the uniformity of the distribution of gravity generated by the aggregate; prevent the transfer of vibration to build structures created by the unit when placing aggregates in the technical premises and on the roof, establishing units for vibration insulators;

Around Chiller, it is necessary to provide free space for air intake to condensers, the possibility and convenience of service work, maintenance and repair of the compressor and heat exchange equipment.

The hydraulic connection of the chiller to the pumping station should be performed by flexible connections, passes through overlaps and walls in the sleeves, without connecting pipes hard with structures.

When used as a coolant, water and placing chiller in the unheated room should be envisaged to drain the water during the cold period of the year.

3. Requirements for the quality of work

Tests of ventilation and air conditioning systems An acceptance of their operation

1. Preparation tests of ventilation and air conditioning systems are conducted by the Working Commission for the Program approved by the Customer.

2. Fully mounted air conditioning systems and air conditioning systems are allowed to the presets, together with automation and remote control systems, tested and commissioning in the scope of approved programs:

On air performance, heat and acoustic measurements and a temperature and humidity regime;

On the sanitary and hygienic effect (for experimental and head samples);

On the sealing of shut-off devices and structures, as well as adjustment of the collective anti-chemical protection system.

3. By the time of testing, the following documents must be presented:

Technical descriptions of systems;

Working drawings and change statements;

Presenter note of the installation organization;

Acts on the acceptance of equipment and premises for installation;

Route passports for installation and commissioning;

Acts of revision of equipment;

Acts of testing of nodes and elements of systems for tightness;

Program of individual tests.

4. The pre-test test includes:

Verification of the quality of work performed;

Checking equipment equipment;

Tests and verification of all aggregates in order to determine technological parameters;

Tests and checking automation systems.

5. When conducting pre-test tests must be:

The performance of the fans is determined;

The compliance of the project of air volumes passing through air-discharge, air-acting, air dust and other devices;

Detected looseness in the ventilation system;

The uniformity of the heating of the calorificates and the operation of the nozzles are checked.

6. Deviations on the performance of fans, flow or air volume throughout the system or passing various devices should not exceed ± 10%. The magnitude of the supply or air leakage due to looser for sociable ventilation should not exceed 10-15%. For special ventilation systems, this value is set by the relevant specifications.

7. Systems of ventilation and air conditioning in the project of individual tests are tested together with remote and automatic control systems. The test results are considered satisfactory if during the testing process there was no failures in the operation of automation and equipment devices, and the deviations of the actual parameters of the operation mode did not exceed the permissible. At the end of individual tests, the act is drawn up, and the Working Commission decides on the admission of the ventilation and air conditioning system to comprehensive tests or commissioning. The purpose of integrated tests is to check the availability of the ventilation system and air conditioning to the operation of the entire complex or the calculated technological load. The systems of ventilation and air conditioning are considered to be the integrated tests, if during testing temperature fluctuations, relative humidity and the concentration of harm in the limits established norms. During the acceptance must be indicated:

Digging from the project made in the production of construction and installation work (agreed with the project organization and the customer);

Characteristics of air ducts, fans, calorifers, electric motors, electrical appliances, germoclapanov, filters, the serviceability of them when working and compliance with project data;

Test results, adjustment and adjustment of ventilation systems, made by assembly and appliance organizations;

The quality of the construction and installation work;

The multiplicity of air exchange in each room of structures in all modes and programs; Actual support or air vacuum.

A set of workers drawings and acts of hidden work are attached to the act.

4. Material and Technical Resources

Tools and fixtures for installation and service of refrigeration equipment

To carry out installation, maintenance and repair of refrigeration equipment, the following set of tools, devices and devices are recommended:

Tool for mounting copper, brass and steel pipes;

Device for soldering and welding pipes;

Devices for vacuuming and refrigeration refrigeration;

Devices for determining the place not tightness of the refrigeration system;

Instruments for mounting the electrical circuit and automation scheme.

When used when installing copper, brass, steel and plastic pipes, various tools are used for high-quality installation work:

Tools for mounting copper and brass pipes;

Tools for mounting steel pipes;

Tools for mounting polymer pipes.

Truborez (Fig. 9) allows you to very purely cut off the copper pipeline of the required length, and when using the knife, it is necessary to process the pipeline (both inner and outer surface) to be treated with a device (Fig. 10) to remove burrs.

Fig.9. Truborez

Fig.10. Fixture for removing sowing with tubes

Fig.11 shows the collapse (elevation) under the nipple compound and the pipeline lifter (Fig. 12) with a mandrel.

Fig.11. Filming

Fig.12. Set of dumplings with mandrel

For flexing pipelines, the pipe bender is manual (Fig.13).

Fig.13. Manual pipe bending

When performing welding, it is necessary to have a welding or solder unit. For pipelines of small diameters, instead of welding, you can use soldering with propane burners. For pipelines of large diameters, a welding unit with an oxygen-acetylene burner is used (Fig.14).

Fig.14. Oxygen-acetylene welding unit

For vacuuming refrigeration refrigerationsystems are recommended to use a refueling station (Fig. 15) or the next set:

Fig.15. Portable refueling station

Manometer collector with low and high pressure gauges, vacuum and hose set (Fig.16);

Two-stage vacuum pump with a vacuum (Fig. 15);

Filling cylinder for controlling refueling or refueling scales. One of the samples of the collector and the methods of its connection are shown in Fig.16.

Fig.16. Portable manometer collector and flexible hose connections

Such a collector has 4 hoses with naked nuts and 4 valves.

For blowing flexible hoses:

A, C, D- open, IN- closed (flexible hose N 2 under pressure) 1, 3, 4 - connected to the collector, as shown in the diagram, but the opposite ends are free; 2 IN- Open, in order to start the purge.

To control the pressure in the contour:

FROMand D.- closed, BUTand IN- open until it stops 1 and 3 - connected, as shown in the diagram; H.and L.- Unscrew until you stop, then wrap on 1/3 turns. Watch pressure.

For contour purge:

BUTand IN- closed, FROMand D.- open, 1 and 3 - connected, as shown in the diagram, 4 - connected by one end to the collector, as shown in the diagram, the other end is free, H.and L. BUT- open at the beginning of the outer purge (through a flexible hose 4).

For refueling refrigerant through the suction housing line:

A, B, D- closed, FROM- Open 1, 2, 3 - connected, as shown in the diagram, H.- unscrew until it stops, then wrap on 1/2 turn, L.- unscrew up to half, IN

To refuel oil through the suction line of the contour:

A, B, D- closed, FROM- Open 1 - connected as shown in the diagram, 2 - connected by one end to the collector, as shown in the diagram, and the other end to the oil tank, H.- Close until you stop, L.- Close until you stop, IN- Slowly open, adjusting oil consumption.

For vacuuming and refueling the contour:

BUTand IN- closed, FROMand D.- open, 1 and 3 - connected, as shown in the diagram, N.and L.- Release until you stop, then wrap on 1/2 turn. If the pressure gauges show the residual pressure, to produce contour before vacuuming, BUT- Open N.and L.- half open 2 and 4 - Connected, as shown in the diagram.

Run the pump and complete vacuuming:

BUT- close, then put the pump, N.- unscrew until you stop, then wrap on 1/2 turnup, D.- closed, IN- Slowly open, adjusting refrigerant consumption.

For definition of refrigerant leakageregardless of its composition, the method of washing or with the help of lactium paper (ammonia or R22, R502) can be used. To determine leaks there is also various equipment. Figure 19 shows a halide lamp, it is used for non-flammable refrigerants during overpressure in the system.

Fig.17. Halogen lamp

With a special addition to the refrigerant, an ultraviolet lamp can be used (Fig. 18) to detect leaks due to the luminescence of the indicator gas in its rays.

Fig.18. Ultraviolet lamp for detecting leaks due to indicator gas luminescence in its rays

The device presented in Fig.19 allows you to detect leaks as refrigerants of the CFS and NSFC category and absolutely not polluting the atmosphere of HFS refrigerants (R134A).

Fig.19. Electronic lecturer for refrigerants CFS, NSFs and YRs

The device presented in Fig.20, whose work is based on the principle of gas ionization located between two electrodes.

Fig.20. Ionization targer for refrigerants CFS, NSFs and HFS

To determine faults in electrical circuitsspecialist refrigerators exist toco-measuring ticks (Fig.21), which allow measurement of voltage (in volts) and electrical resistance (in Omah).

Fig.21. Clamp metering

The use of current testers in the module mode allows:

Check indirectly by resistance to windings of compressor electric motors, fan for compliance with specifications;

Detect a closure on the ground in the winding of the electric motor;

Establish the belonging to the terminals of the electric motor to the starting and chassis windings by measuring their resistance;

Identify short-circuited windings;

Check the relay or contactor contacts.

The use of current testers in a voltmeter mode allows:

Check the voltage on the terminals of the electric motor;

Reveal the linear and zero phases, as well as ground wire;

Check the correctness of the grounding of electrical systems; Check fuses;

Detect voltage jumps or wandering currents. The use of current ticks in the ammeter mode allows:

Check the power of the start current;

Check electrical systems on increasing;

Adjust unloading when starting with increasing time;

Check the primary winding in the current transformer;

Distinguish a star connection from a triangle connection;

Check the phase unbalancement;

Check the stream of the stroke rotor for compliance with the data specified on the engine housing.

Refrigerants and colasters

Refrigerator agent (refrigerant)it is a working body of a refrigerating machine, changing its aggregate state in the process of passing in elements of equipment operating both by direct cycle (cooling mode) and in the reverse cycle (thermal pump mode). Selecting heat from the environment, refrigerant boils, moving from liquid to a gaseous state. Due to the endothermic nature of the process, cold is produced. The heat selected in the air is removed from the refrigeration machine during the process of transition of the refrigerant from the gaseous state into the liquid under the exothermic process in the condenser.

The substances used in the refrigeration should have a low boiling point at atmospheric pressure, boiling vapors should not be too large, but condensation pressure is not too high. It must be non-aggressive in relation to structural materials and oils, as far as possible toxic, non-flammable and explosion-proof.

Table 4.1 lists the main refrigerants currently used and intended for use in the future.

Table 4.1.

The main refrigerants currently used and intended for use in the future

Designation

Name

Trichloromethane

Dichlorodifluoromethane

Bromohlordifluoromethane

Trifluorchloromethane

Bromthrifluoromethane

Diftorchloroman

Trifluoromethae

Difluoromethane

Trichlortrifluoroethan

Dichlorottrafluoroethane

Chloropentafluoroethan

Dichloritrifluoroethane

Chloretrafluoroethan

Pentafluoroethan

Tetrafluoroethan

Dichlorfluoroethan

Chlordifluoroethan

Trifluoroethan

Difluoroethan

Carbon dioxide

Table 4.2 presents the main physical properties and maximum permissible concentrations of refrigerants that are most frequently used in the SD and recommended for use in the future.

Table 4.2.

Group of refrigerants used in Hu SCV, their physical properties

Chest

Check-room number

Chemical name

Chemical formula

molecule

large mass

Gas constant, J / (kg · k)

Boiling point at 101.3 kPa, ° C

Frozenation temperature, ° C

Critical temperature, ° С

Ftorotrichloromethane

Diftoridichloromethane

Diftorombrommethan

Trifluorchloromethane

Trifluorombromomethane

Difluoromethane

Trifluoromethae

Trifluorichlorethan

Tetraftorudichlorethan

Pentafluorchloroethan

R12 (73.8%) + R152A (26.2%)

R22 (48.8%) + R115 (51.2%)

Carbon dioxide

Methylene chloride

Methyl chloride

Ethyl chloride

Methyl formate

Sulfur dioxide

Dichloroethylene

Isobutan

Propylene

The standard NF E35-400 divides refrigerants into three groups:

I Group - non-toxic and non-flammable refrigerants.

Group II - refrigerants with a certain degree of toxicity.

III Group - refrigerants according to the degree of ignition and the formation of explosive mixtures with air at the lower concentration limit of 3.5% by volume.

The NF E35-400 also specifies the conditions for the use of various refrigeration systems, as well as their location and conditions for gasket pipelines for transporting refrigerants, depending on the group, to which this refrigerant belongs, as well as room categories.

In connection with the environmental issues, the prospects for using ammonia as a working fluid in refrigeration plants of air conditioning systems began to be considered. Ammonia is less harmful to environmentally friendly, affordable and has excellent thermodynamic qualities.

The main disadvantage of ammonia is its toxicity, flavors in certain concentrations and incompatibility with copper.

The use of refrigeration plants using ammonia as a refrigerant must be carried out by enterprises and organizations that have a license to perform this type of work, and projects must be agreed in the Russian State University. It is forbidden to use refrigeration plants with direct cooling (direct boiling of refrigerant in the air cooler) for comfortable air conditioning in administrative and industrial premises.

The refrigerants, with the exception of refrigerants II and III groups, belong to explosion-proof and non-toxic chemical compounds or mixtures, however, when opening with open fire, fluorine and chlorine-containing refrigerants are decomposed with the release of chlorine and phosgene compounds (neuro-paralytic gas).

When a fire occurs in rooms where refrigeration plants are located, you should use insulating or filtering gas masks. With an increase in the concentration of freon vapors in the room, the oxygen content drops and promises, as the density of most refrigerants is more air density and during leakage, it tries to take lower levels in the premises. It is not recommended to fill in more than 80% by volume of tanks for refrigerants.

Claimersthey are an intermediate body, with the help of which heat transfer from the air of the cooled room to the refrigeration agent. The coolant can serve water, aqueous solutions of salts or liquids with a low freezing temperature - antifreeze, etc. Claimers are used where direct cooling is undesirable or not submitted.

Common coolars are sodium chloride (NaCl), calcium chloride salts (CACL), glycolic aqueous solutions. Due to the high corrosive activity of salt solutions, the cost of repair during the operation of the equipment is significant, so currently finding solutions of polyhydric alcohols, such as propylene glycol (PG), ethylene glycol, glycerin, which is characteristic of central air conditioning systems. When designing and installing systems with glycolic coolants, their physico-chemical features should be taken into account. Glycols have a smaller molecular size, which leads to the formation of leaks (especially at low temperatures and high concentrations), with the improper selection of the gasket material in seals. It is not recommended to use galvanized steel pipes in systems with glycolic colasters.

For first aidwith the defeat of man, the refrigerant should be in the first-aid kit ammonia, valerian drops, drinking water, ointment of Vishnevsky or penicillin ointment, sterile napkins, bandages and cotton.

In case of poisoning by freon refrigerants, before the arrival of the doctor, the victims are carried out on fresh air or into a clean warm room. The victim is given to inhale oxygen for 30-40 minutes, warmed by the heating plates, allow the ammonia alcohol from the sweat and drink strong tea or coffee.

During the damage to the mucous membrane, we have a 2% solution of soda or water. If you get into your eyes, they are rich enough with clean water.

The refrigerant hitting the skin is frostbite. The affected places are wetted with warm water, and then the affected surface is dried and put the ointment bandage.

5. Environmental protection and safety regulations

Occupational safety measures when installing and operating ventilation systems and equipment, air conditioning,

pneumatic transport and aspiration

Work on the installation of ventilation systems in a significant part is made at high altitude. Upper works are considered all installation works that are performed at an altitude of more than 5 m from the surface of the soil, overlap or working flooring.

Workers are allowed not under 18 and not over 60 years old, who have passed a special medical examination.

The safe execution of installation work at the height requires the use of reliable stairs, forests, scaffolds, tips, lugs, etc.

When using metal stairs, their height should provide a work opportunity to work standing on the step, being at a distance of at least 1 m from the upper end of the stairs; At the same time, the worker must consolidate the Carabin of the assembly belt to reliable elements of building structures. The lower ends of the filter stairs must have stops in the form of sharp thickens or rubber tips, the upper - to be fixed to the solid structures.

When making the installation of air ducts with suspended lugs, workers should be attached to safety belts to an insurance steel rope having an autonomous suspension. PVU-2 safety belts are calculated on the maximum mass of the incident man 100 kg and the length of the braking path 0.75 ... 1.5 m. The PAU-2 device, attached to the construction structure with a circuit with a length of about 1 m, allows the worker to move to a distance equal to The length of the brake cable is 10 m. The brake cable is attached to the safety carbine safety belt.

In the process of installing air ducts, it is forbidden to be under the mounted air duct, switch around the farms and other building structures during operation at height, and also work without securing the safety belt. In dangerous locations, it is necessary to secure the safety belt for the steel insuring cable, specially stretched for this.

When installing, the technological sequence of delivery of air ducts and ventilation equipment should be strictly observed to places of installation and install them into the project position without creating cramped conditions in the workplace.

All lifting facilities, inventory and tools must comply with the nature of the work performed and be in good condition. Before installation, the manufacturer of works or master is required to check the lifting mechanisms, rigging devices and register check results in a special journal.

Places of installation of lifting facilities, as well as the fastening of lever winches, tags and blocks to building structures should be coordinated with the general contractor. Without the permission of the construction organization's management organization, the implementation of these works is not allowed.

When installing load-lifting devices on overlaps, it is necessary to arrange the bases for the distribution of the concentrated load on the large area.

Installations performing rigging work must be trained in a special program and have a certificate for the right to produce rigging work.

The sling of the ventilation equipment and the fastening of winches, tags and blocks to building structures should be made in accordance with typical technological cards.

BIBLIOGRAPHY

GOST 30494-96. Buildings Residential and public. Parameters of microclimate in rooms.

GOST 12.1.003-83. CBST noise. General security requirements.

Avok Standard. Buildings Residential and public. Norms of air exchange.

SNiP 23-01-99. Construction climatology.

SNiP 23-02-03. Thermal protection of buildings.

SNiP 2.04.05-91 * (ed. 2003). Heating, ventilation and air conditioning.

SNIP 2.08.01-89 *. Residential buildings.

SNIP II-12-77. Protection against noise.

Sanpin 2.1.2.1002-00. Sanitary and epidemiological requirements for residential buildings and premises.

CH 2.2.4 / 2.18.562-96. Noise in workplaces in the premises of residential, public buildings and in the residential building.

MHSN 3.01-01. Residential buildings.

MHSN 2.04-97. Permissible levels of noise, vibrations and sound insulation requirements in residential and public buildings.

Manual for MGSN 2.04-97. Design of sound insulation of the enclosing structures of residential and public buildings.

Snip 12-03-2001 Labor safety in construction. Part 1. General requirements.

SNiP 12-04-2002. Labor safety in construction. Part 2. Building production.

GOST 12.2.003-91. SSBT Production equipment. General security requirements.

GOST 12.3.009-76. SSBT Works loading and unloading. General security requirements.

GOST 24258-88. Forming means. General specifications.

PPB 01-03. Fire safety rules in the Russian Federation.

Technical information SCS "Stroithechnologist".

Documents DB "TEKHEXPERT".

Electronic document text

prepared CJSC Codex and drilled on materials,

provided by k.t.n. Demyanov A.A. (VITU)


Typical technological map on the installation of ventilation and air conditioning systems

Installation of air ducts

1 AREA OF USE

Typical technological card (TTK) is compiled on one of the options for the installation of air ducts of ventilation systems of industrial and public buildings.

TTK is designed to familiarize workers and engineering and technical workers with the rules for the production of works, as well as to use in the development of projects for the production of works, projects of the organization, other organizational and technological documentation.

2. General provisions

Ventilation systems. Modern duct installation techniques

In the total work on the installation of ventilation systems, air conditioning, pneumatic transport and aspiration on industrial facilities - the most time consuming is the installation of air ducts.

Most of the installation of air ducts It is necessary to perform at an altitude, which complicates the process of assembling the ventilation systems, especially if you consider significant overall dimensions and a lot of parts of the ventilation equipment. This causes the need to use when installing ventilation of special machines, mechanisms and fixtures. These include machines such as self-propelled cranes, autohydripeds, balances of retractable self-propelled, mobile mounting sites, etc.

When applying ventilation systems, the installation method of air ducts depends on the features of the design of the ventilation systems, the characteristics of building structures, the conditions of installation of ventilation, the presence of lifting mechanisms.


The most progressive method of installation of air ducts provides a preliminary assembly of air ducts and integrated nodes with a length of 25-30 m, composed of direct portions of air ducts and shaped parts.

Ventilation systems. Installation of horizontal metal air ducts

When installing horizontal metal air ducts, such a sequence of work must be observed:

Install the mounting means by welding to mortgage parts or using a construction and assembly pistol;

Charge places to install mechanisms for lifting duct nodes and prepare inventory forests, scaffolding, towers;

Separate parts of the air ducts and collect them in the integrated nodes on the inventory stands, and the parts of the air ducts of large sections - on the floor;

Install clamps or other mounting tools.

After an intermediate assembly of the air ducts, the assembly assembly is traveled by inventory slings, and at the ends of the nodes tie out the deficule of the hemp rope.

Mounting unit duct Raise to the project mark with inventory lifter or other mechanisms, then hang it to previously installed mounts. At the end of the installation, the air duct is connected by flanges with a previously mounted duct section.

In the installation practice there are such variants of design solutions of laying metal air ducts, as a laying under the overlap of the building, on the outer wall, the overpass, in the inter-proprietary space.

When installing air ducts, the following basic requirements of SNiP 3.05.01-85 "Domestic Sanitary Systems" should be observed.

The method of mounting the air ducts is chosen depending on their position (vertical, horizontal), the nature of the object, local conditions, location relative to building structures (inside or outside the building, in the wall, in the columns, in the inter-estimal space, in the mine, on the roof of buildings), and Also from solutions laid out in the PPR or typical technological maps.

Air ducts of ventilation systems, air conditioning and air heating should be designed in accordance with the requirements of SNiP items 2.04.05-91, providing technical solutions in projects providing maintainability, explosion-saving systems and regulatory requirements.

Mounting positions, methods of compound and fixing ducts

In order to unify the location of the air ducts regarding building structures, it is recommended to use the installation provisions of the circular and rectangular air ducts of the circular and rectangular cross section. These mounting positions of air ducts are determined by the following guidelines and sizes.

1. The axes of the air ducts must be parallel to the planes of building structures.

2. Distance Div_adblock269 "\u003e


https://pandia.ru/text/80/230/images/image003_209.gif "width \u003d" 37 "height \u003d" 24 src \u003d "\u003e - the maximum diameter of the duct paved, including insulation, mm;

For rectangular air ducts

https://pandia.ru/text/80/230/images/image005_174.gif "width \u003d" 33 "height \u003d" 24 src \u003d "\u003e. gif" width \u003d "25" height \u003d "15 src \u003d"\u003e. GIF "width \u003d" 25 "height \u003d" 15 src \u003d "\u003e 400 mm.

3. The minimum allowable distance from the axis of the air duct to the outer surface of the electrical conductors is determined by the formulas:

https://pandia.ru/text/80/230/images/image009_147.gif "width \u003d" 117 "height \u003d" 24 src \u003d "\u003e, mm.

4. The minimum allowable distance from the axis of the air duct to the outer surface of the pipelines is found according to the formulas:

For round air ducts

https://pandia.ru/text/80/230/images/image004_198.gif "width \u003d" 100 "height \u003d" 24 src \u003d "\u003e, mm.

5. With a parallel laying of several air ducts at one mark, the minimum allowable distance between the axes of these air ducts is calculated by the formulas:

For round air ducts

https://pandia.ru/text/80/230/images/image012_129.gif "width \u003d" 155 "height \u003d" 24 src \u003d "\u003e, mm;

where https://pandia.ru/text/80/230/images/image013_125.gif "width \u003d" 37 "height \u003d" 24 src \u003d "\u003e - diameters of air ducts, mm; and - sizes of the sides of the air ducts of the rectangular section, mm.

6. The minimum allowable distance from the axis of air ducts to the surface of the ceiling is determined by formulas:

For round air ducts

https://pandia.ru/text/80/230/images/image004_198.gif "width \u003d" 100 "height \u003d" 24 src \u003d "\u003e.

7. When passing air ducts through building structures flange and other detachable compounds of air ducts place at least 100 mm from the surface of these structures.

Separate parts of the air ducts (straight sections and shaped parts) are connected to the aircraft network using flange and inflaming compounds (bandages, slats, rails, fuse and other connections).

Fastening the air ducts should be performed in accordance with the working documentation and the requirements of SNiP 3.05.01-85 *. Fastening horizontal metal uninsulated air ducts (clamps, suspensions, supports and others) on the Beschatine Connection should be installed in the following distances:

Not more than 4 m with diameters of the circular duct or sizes of the larger side of the rectangular duct less than 400 mm;

Not more than 3 m with diameters of the circular duct or size of the larger side of the rectangular duct 400 mm and more.

Fastening horizontal metal uninsulated ducts on the flange compound of the circular cross section with a diameter of up to 2000 mm or a rectangular section with the size of a larger side of it to 2000 mm inclusive should be set at a distance of not more than 6 m. The distance between the fasteners of the insulated metal air ducts of any transverse sections, as well as uninsulated air ducts The circular cross section with a diameter of more than 2000 mm or rectangular section with the size of its main side more than 2000 mm must be assigned to working documentation.

Mounting vertical metal air ducts should be set at a distance of no more than 4 m.

Fastening vertical metal air ducts indoors with floor height more than 4 m and on the roof of the building should be assigned to a work project.

The designs of the compounds of the duct parts will be considered in more detail in the special literature.

Development of technical documentation for the manufacture and installation of air ducts

The development of technical documentation for the manufacture and installation of air ducts is reduced to the development of an axonometric mounting scheme of the ventilation system (air conditioning), components of the parts of the air ducts and serial production vendors (silencers, dampers, air distributors, umbrellas, deflectors, etc.), as well as drawings (sketches) non-domestic details. The listed technical documentation is called the installation or installation and procurement (MZP) project.

MZP is needed for placing an order in the procurement plant to make parts of the air ducts of mounted ventilation and air conditioning systems, to test the completeness of the workpieces of systems, as well as to determine the place of each part performed on the production plant in the system during its installation. MZP is developed for each system.

The following source data is required to develop MP:

Working drawings of the brand of mounted systems and architectural and construction drawings of the Marka AR, plans and cuts of the building (facilities) in the location of the mounted systems;

Albums and other materials containing data on unified items and nodes of mounted systems;

Overall and connecting dimensions of equipment and typical parts;

Regulatory and methodological materials on the procedure for performing and designing MP systems.

Mounting design consists of the following steps:

Using the RF brands of the OE, draw the axonometric scheme of the system, produce the division of the tracks of the system air ducts into parts, as a rule, unified contained in albums, norms and other documents;

Select the types of connecting parts between themselves and with other assembly units of the system;

Install places and types of fixtures of the system of air ducts system;

Develop sketches (drawings) of non-dopeful parts with the definition of all the dimensions necessary for them;

Documents are required for MP:

1) AXONOMOMETRIC CONTROL SYSTEM SYSTEM;

2) components;

3) Sketches for non-competitive (non-type, non-standard) details.

Other documents can be developed. There is no state standard or other unified standards on the composition of MP documents, and therefore their list in different regions and enterprises may differ. Mandatory documents are the three names listed above. However, their structure, as well as the content may differ.

Axonometric mounting scheme Draws out based on the axonometric scheme of the working drawing developed by the project organization before starting the installation design, i.e. it is available as source data. Aksonometric mounting scheme may be by configuration a copy of the RF scheme either is depicted arbitrarily on a separate sheet without scale. This scheme applies marks of the levels of the fan, overlap, lifts, dipped ducts, as well as the length of horizontal rectilinear sites and all diameters and cross-section of air ducts. Figure 1 shows for comparison of axonometric diagrams of the same ventilation system and an axonometric scheme from the composition of the working drawings and the assembly circuit.

Fig.1. Axonometric ventilation system schemes:

but - Drawing diagram; b. - mounting scheme; 1...14 - Unified details

The scheme is divided into parts (details). First, the standard, typical and unified system parts are distinguished, the dimensions of which are known. Then the sketches of the inadicular (non-discorded) parts in the axonometric projection are developed, the dimensions needed for their manufacture are determined. Find the total lengths of direct networks between standard, typical, fittings and other elements. The rectilinear total areas of air ducts are divided into individual sections (parts) of the recommended VN 353-86 length. At the same time, one of the individual sections of each straight line of air ducts may differ from the recommended length. He's called submer. The length of the amount is usually specified at the place, and therefore it is appropriate with the flange compound one flange to make free to move along the axis of the air duct. The areas are assigned numbers, they are denoted by numbers in circles, for example (T), which means the section number 1. In Fig. 2 shows a simplified fragment of the axonometric mounting circuit of the air ducts of the ventilation system. The fragment is used to illustrate simplified components (Table 1.1).

Fig.2. Fragment of the mounting scheme of air ducts:

1 , 2 , 3 - straight sections; 4 - direct plot with the end grid; 5 - direct plot with mesh and engine; 6 - direct plot with inserting; 7 , 8 - taps; 9 - Transfer

It is noted above that the design of the MP includes the development of components and statements of the parts of the air ducts.

On each system is compiled one or several components. The number of statements and their form depends on the requirements of enterprises performing an order for the manufacture of parts. For example, in the bundle of the ventilation system, the following data can be given: Rooms of parts, their names, dimensions of parts (diameter for round-section air ducts; sizes of the sides of the air ducts of rectangular section; lengths), quantity (pieces, kg of one thing and the mass of all pieces ), metal thickness. The parts themselves are listed in the statement not in the sequence in which they are located in the system in the course of air, but by groupings of the same type:

Straight sections;

Straight sections with inserts;

Straight areas with lattices, grids, etc.;

Taps and shares;

Transitions;

Boxes.

The composition of the groups and their order of location in the statement in various regional organizations may differ.

The sample of the components is presented in Table 1.1, which is compiled for a fragment of the system shown in Fig. 2. At the end of the complete statement, data can be given data to the total area of \u200b\u200bthe surface of the air ducts and the overall areas in the thickness of the metal, parts (separately according to direct areas and the shaped parts, in terms of metal thickness in M \u200b\u200band kg); the number and list of connecting elements (bandages, flanges and connections on the bus - the amount for each size); Lattices and grids, VEPS (air distributors of ejection panel stamped) and other parts mounted on air ducts.

Table 1.1.

Packing Interior Details

N.
details

the name of detail

Diameter, mm.

Length, mm.

Quantity, pcs.

Surface, M.

Note

Direct site

Mesh with engine 200x200 mm

Straight plot

Straight plot with mesh and engine

Straight

Typical technological card on the installation of ventilation is compiled for systems forced ventilation, including the network of air channels. Its main purpose is to familiarize workers and engineers with how work should occur on the installation of ventilation channels, assistance in the location of the equipment indoors, the correct distribution of technological processes, which will continue to occur in production and so on.

How to install ventkanals

Most of the work in the installation of air conditioning and ventilation systems takes the installation of ventilation channels.

Industrial ventilation

And this is not strange, because they are placed inside the entire building, if the premises are used for industrial purposes, then it is also large dimensions, plus it is often necessary to install at high altitude, and this greatly complicates the case. As a result, you have to resort to the help of special machines and equipment. Most often it is self-propelled cranes, mobile mounting sites, autohydripes and so on.

The complexity of installation affects the mass of factors:

  • The complexity of the designed system;
  • Features of the building of the building;
  • Surrounding conditions, etc.

To simplify the technological process of installing air ducts, nodes consisting of direct portions of ventilation pipes and shaped parts are made in advance. After installing each node, you need to be checked with data that carries a technological card on the installation of ventilation.

Stages of installing horizontal metal ventkanalov

To qualitatively install the network of ventilation channels, you need to adhere to a certain action algorithm.

Fastening

The first fastening means are installed. It is done with their welding to mortgage details or using a special mounting gun. The places where the lifting mechanisms will be located, the scaffolding, tower and so on are prepared. On the inventory supports, small parts are collected into the nodes, nodes from large vantkanals are made on the floor. Clauses and other mounts are installed.

When the intermediate preparation is over, the nodes are triggered, tights from the rope are tied at the ends of the nodes.

Preparatory work is over, you can start mounting. With the help of special lifting mechanisms, the nodes are summarized to the previously marked places and hang to the attachments. It remains using the flange, attach part of the system to the previously mounted node.

There are other options for mounting air ducts. The method is chosen depending on their position in space, the characteristics of the industrial facility, the surrounding conditions, the location of the air ducts (inside or outside the building) and other things.

If the ventilation system includes air conditioning and air heating, it should be designed according to all items SNIP 2.04.05-91, while providing for the possibility of breakdown and repair, and regulatory requirements.

Main mounting provisions

It is important to correctly arrange the ventilation channels in relation to building structures. For this, special recommendations have been developed that allow you to correctly fasten the air ducts of round and rectangular sections. The main recommendations and dimensions are shown below.

The axes of the ventilation pipes are placed in parallel planes, next to which they are mounted. It is necessary to choose the right distance (taken in millimeters) from the wall plane (ceiling, floor) to the axis of the pipe. If channels with a circular cross section are used: l \u003d 0.51dmax + 50, where Dmax is the largest diameter of the air duct, including the insulator.

Ventilation channels

In the case of using channels with a rectangular section, the formula looks like this: l \u003d 0.5bmax + x, where Bmax is the maximum channel width; x - the distance between the outer surface of the pipe and the wall should be at least 5 cm.

It is accepted that for pipes from 10 to 40 cm x \u003d 10 cm, 40 ... 80 cm x \u003d 20 cm, 80 ... 150 cm x \u003d 40 cm. It is important and the distance from the channel axis to the electric pipe. Air ducts with a circular cross section: L \u003d 0.5DMAX + 300. With a rectangular cross section: L \u003d 0.5Bmax + 300.

If there are two ventilation branches in parallel, then follow the next minimum distance between their axes. Round cross section: L \u003d 0.5 (Dmax + d'Max) +250. Rectangular section: L \u003d 0.5 (BMAX + B'max) + x.

In the case when the ventilation pipes are attached under the ceiling, you must also comply with the minimum distance to it. Round cross section: L \u003d 0.5DMAX + 100. Rectangular: L \u003d 0.5Bmax + x. If the air ducts pass through building structures, then the distance in 10 centimeters should be observed.

Connection of air ducts

The network of ventilation channels consists of separate small parts that are connected to each other with the help of bandages, rails, slats, commercial and other connections.

Details of air mainstream

To properly fix the ventilation pipes, you should use working documentation and relevant requirements. If in the reinforcement process, inflaming compounds are used, then the following distances between them are followed:

  • When using pipes with a diameter of less than 400 mm, the distance must be no more than 4 meters;
  • If the diameter is 400 mm and more, then the distance becomes up to 3 meters.

When installing air ducts in a horizontal position with a circular cross section of the diameter of which up to 2000 mm or rectangular with a side up to 2000 mm, the distance between the attachments is received by no more than 6 meters.

If the pipes are installed in a vertical position, then the distance between the fasteners is up to 4 meters.

Mounting design

Before installing the highway for ventilation, it is necessary to make an assembly design. It consists of several main stages.

Aksonometric scheme

At the first stage, the axonometric scheme of the system is drawn, then the network of air channels is divided into separate parts. Next, you should choose a method for connecting small components between yourself and with larger nodes. Places are determined where fasteners will be located in the future. Sketches of non-standard details are also made, where all the necessary sizes are indicated for their manufacture. And in the end documents are drawn up for mounting design:

  • Drawings of non-standard parts;
  • Accidentometric scheme;
  • Packing Vedomosti.

Depending on the region where the installation of the ventilation system will depend on the set of necessary documents. But those three that were listed above will always be present.

Installation of air ducts on an industrial facility

Typical Technology Card (TTK)

Installation of metal air ducts internal ventilation systems

I. Scope

I. Scope

1.1. Typical technological card (hereinafter referred to as the TTK text) is a comprehensive organizational and technological document, developed on the basis of the scientific organization of labor to carry out the technological process and the determining composition of production operations using the most modern means of mechanization and methods for performing work on a certain given technology. TTK is intended for use in the development of projects for the production of work (PPR) by construction departments.

1.2. In this TTK, indications of the organization and technology of work on the installation of metal air ducts of internal ventilation systems are determined, the composition of production operations, the requirements for quality control and acceptance of works, the planning complexity of works, labor, industrial and material resources, industrial safety and labor protection measures .

1.3. The regulatory framework for the development of a technological card is:

- typical drawings;

- Construction standards and rules (SNiP, CH, SP);

- factory instructions and technical conditions (TU);

- norms and rates for construction and installation work (GESN-2001 Yenir);

- production rates of consumption of materials (NRRM);

- Local progressive norms and rates, labor costs, the rate of consumption of material and technical resources.

1.4. The purpose of creating TTK is a description of the decisions on the organization and technology of work on the installation of metal air ducts of internal ventilation systems, in order to ensure their high quality, as well as:

- reducing the cost of work;

- reduction of construction duration;

- ensuring the safety of the work performed;

- organization of rhythmic work;

- rational use of labor and machines;

- Unification of technological solutions.

1.5. On the basis of the TTK as part of the PPR (as mandatory components of the project's work project), working technological maps (RTC) are developed for the implementation of individual types of work on the installation of metal air ducts of internal ventilation systems.

The design features of their execution are solved in each particular case of the work project. The composition and degree of detailing materials developed in RTK are established by the corresponding contract construction organization, based on the specifics and volume of work performed.

RTC is considered and approved as part of the PPR by the head of the General Contracting Construction Organization.

1.6. TTK can be tied to a specific object and conditions of construction. This process is to clarify the amount of work, means of mechanization, the need for labor and material and technical resources.

Procedure for binding TTK to local conditions:

- consideration of card materials and choosing the desired version;

- checking the compliance of the initial data (work volumes, time standards, brands and types of mechanisms used by building materials, the composition of the workers' link) adopted option;

- adjustment of work volumes in accordance with the selected version of the work of work and a specific project decision;

- crosses the calculation, technical and economic indicators, the need for machines, mechanisms, tools and logistical resources in relation to the chosen version;

- Registration of the graphic part with a specific binding of mechanisms, equipment and devices in accordance with their actual dimensions.

1.7. The typical technological card was developed for engineering and technical workers (manufacturers of works, masters, brigadiers) and workers performing work in the II Road and Climatic Zone, in order to familiarize them (training) with the rules for the installation of metal air ducts of internal ventilation systems, With the use of the most modern means of mechanization, progressive structures and methods for performing work.

The technological card is developed for the following works:

II. General provisions

2.1. The technological card was developed on a set of work on the installation of metal air ducts of internal ventilation systems.

2.2. Work on the installation of metal air ducts of internal ventilation systems, performed by a mechanized detachment into one shift, the duration of working time during the shift is:

2.3. The work that consistently performed during the installation of metal air ducts of internal ventilation systems includes the following technological operations:

- collecting made parts of ventilation;

- installation of the ventilation system according to the design scheme;

- Complete operation of the ventilation system.

2.4. The technological map provides for the execution of works by a complex mechanized link in composition: mobile gasoline power station Honda ET12000. (3-phase 380/220 V, n \u003d 11 kW, m \u003d 150 kg); welding generator (Honda) EVROPOWER EP-200X2 (one-position, gasoline, p \u003d 200 A, H \u003d 230 V, weight M \u003d 90 kg); automotive boom crane ks-45717 (load capacity Q \u003d 25.0 t); mast Lift PMG-1B-76115 (with a lifting capacity of q \u003d 0.5 t, the height of the lift H \u003d 76 m, the rate of lifting V \u003d 0.31 m / s).

Fig.1. Power station

Fig.2. Welding generator

Fig.3. Male lift

Fig.4. Cargo Characteristics of automotive boom crane KS-45717

Fig.5. Electroshlyfmaschinka

Fig.6. ATLAS COPCO XAS 97 compressor

2.5. For installation of metal air ducts internal ventilation systems, the following building materials are used: electrodes 4.0 mm E-42 according to GOST 9466-75; emale PF-133 according to GOST 926-82 *; gF-021 primer According to GOST 25129-82.

2.6. Work on the installation of metal air ducts internal ventilation systems should be performed, guided by the requirements of the following regulatory documents:

- ;

- Snip 3.05.01-85

- Snip 3.05.05-84. Technological equipment and technological pipelines;

- One hundred Nostroy 2.15.70-2012. Engineering networks of high-rise buildings. Device of heat supply systems, heating, ventilation, air conditioning and cold supply;

- One hundred nostroy 2.33.14-2011. Organization of construction production. General provisions;

- One hundred nostroy 2.33.51-2011. Organization of construction production. Preparation and production of construction and installation works;

- Snip 12-03-2001. Labor safety in construction. Part 1. Common Requirements;

- Snip 12-04-2002. Labor safety in construction. Part 2. Construction Production;

- RD 11-02-2006. Requirements for the composition and procedure for conducting executive documentation in the construction, reconstruction, overhaul of capital construction and requirements imposed on acts of examination of works, structures, sections of engineering and technical support networks;

- RD 11-05-2007. The procedure for maintaining a common and (or) special journal for carrying out work in the construction, reconstruction, overhaul of capital construction facilities.

III. Organization and technology for performing work

3.1. In accordance with the SP 48.13330.2001 "SNIP 12-01-2004 Organization of construction. Actualized editorial office" Prior to the start of construction and installation work at the facility, the Contractor is obliged in the prescribed manner to receive project documentation and permission from the Customer to perform construction and installation work. . Performance without permission (warrant) is prohibited.

3.2. Prior to the production of work on the installation of metal air ducts of internal ventilation systems, a complex of organizational and technical measures must be carried out, including:

- develop RTK or PPR on the installation of metal air ducts of internal ventilation systems and coordinate with all subcontractors and suppliers;

- to solve the main issues related to the material and technical support of construction;

- appoint persons responsible for the safe production of works, as well as their control and quality of implementation;

- to negotiate members of the Safety Brigade;

- establish temporary inventory household premises for storing building materials, tools, inventory, workers heating, food reception, drying and storage of working clothes, bathrooms, etc.;

- provide a plot approved for the production of works by working documentation;

- Develop schemes and arrange temporary driveways for the movement of transport to the place of production and platforms for the placement of materials and structures;

- prepare for the production of work machines, mechanisms and equipment and deliver them to the object;

- provide workers with manual machines, tools and means of individual protection;

- ensure the construction site by fire inventory and alarm means;

- protect the construction site and put warning signs lit at night;

- ensure communication for operational dispatching management of work;

- to deliver the necessary materials, devices, inventory, tools and means for safe work in the area of \u200b\u200bwork;

- try the construction machines provided for by RTK or PPR;

- draw up an act of readiness of the object to the work of work;

- Get the Customer's technical supervision permission to start the production of works (clause 4.1.3.2 of the RD 08-296-99).

3.3. General provisions

3.3.1. Ventilation - adjustable air exchange indoors, serves mainly to create an air environment favorable for human health that meet the requirements of the technological process, the preservation of equipment and building structures of the building, storage of materials and products.

3.3.2. A person, depending on the kind of activity (energy costs), stands out into the surrounding air:

- heat (100 kcal / hour and more);

- Water pairs (40-70 g / h);

- carbon dioxide (23-45 l / h).

Production processes may be accompanied by immeasurably large discharge of heat, water vapor, harmful vapors, gases and dust. As a result, the air in the room loses hygienic qualities favorable for well-being, health and human health.

3.3.3. Hygienic requirements for ventilation are reduced to maintaining certain meteorological conditions of air (temperature, humidity and mobility) and its purity.

3.3.4. The essence of ventilation is as follows: the trim air is mixed with the air of the room and as a result of the heat exchange or mass transfer occurring in the room, the specified air parameters are created.

3.3.5. Installation of ventilation systems are carried out in accordance with the requirements of SNiP, a working project, a project for the production of works and instructions of equipment manufacturers. Replacing the materials and equipment provided by the project is allowed only in coordination with the project organization and the customer.

3.3.6. Installation requirements for ventilation systems are reduced to ensure the design parameters of the air environment in ventilated areas. This is achieved with maximum sealing of air ducts and equipment systems necessary sound insulation, proper conditions for operation, repair and replace equipment.

3.3.7. Mounting and Assembly Works Conditions, while maintaining their high quality, is achieved by high industrialization of works, which consists in using standard ventilation chambers, blocks and duct units (shaped parts - diffuser, confusion, knee, tees, crosses; regulatory devices - valves , Sewberry, throttle devices; mounts; pendants; brackets; brackets; flanges) of factory manufacture or made in workshops with appropriate mechanical equipment. In place, as a rule, only collectable parts, applying mechanisms for moving blanks and ventilation equipment.

3.4. Preparatory work

3.4.1. Prior to the start of the work on the installation of ventilation systems, the following preparatory work should be performed:

- The object is adopted by the employees of the assembly organization for the act of technical readiness of the zero cycle to the installation of columns. The act must be made by executive geodesic schemes with applying the position of foundations in terms of and height;

- to carry and store columns on an optional warehouse;

- to select columns and connecting parts that have passed input control;

- Apply in four places at the level of the top plane foundations of the risks of installation axes in accordance with the project;

- Apply the risks of the installation, longitudinal axes on the side edges of the columns, at the bottom of the columns. Risks are applied with a pencil or marker. Unacceptably applying scratches or cuts on the surface of the columns;

- Deliver the necessary mounting tools, fixtures and tools to the edge zone.

3.4.2. When accepting an object for installation of ventilation systems should be checked:

- compliance with all the requirements of SNIP and existing technical conditions;

- the presence and proper registration of acts for hidden work;

- geometric dimensions and bindings to the building structures of foundations for ventilation equipment and air conditioners, supporting structures on the roof of the building for the installation of roof fans and deflectors, holes for the passage of air ducts, assembly openings;

- the correct installation of mortgage parts;

- device of fences of openings, flooring and canopies.

Acceptance of an object for installation should be carried out by employees of the assembly organization on the act.

3.4.3. When transporting air ducts, depending on their species and dimensions, it should be provided:

- for small cross sections - containing or packing;

- for ducts of large sections - telescopic laying;

- For semi-finished products - special packaging.

3.4.4. Loading and hardware and rigging work at the facility are made using workers that are part of the crew of installers. As a mechanized lifting facility at the facility use automotive boom crane KS-45717 and Mast Lift PMG-1B-76115 .

3.4.6. The lines of air ducts and ventilation is recommended to produce inventory goods. The slings should be chosen depending on the type, the mass of the lifted cargo and the method of the lines. The most common slings are shown in Fig. 7.

Fig.7. Slings

but - lightweight sling with loops; b. - lightweight sling with hooks; in - four-letter slop

The lifting load should be held from rotation of the dents. For horizontal elements of the ventiysystem (enlarged air duct nodes), two dehydrations should be used, from the hemp ropes with a diameter of 20-25 mm or with detensions of steel ropes with a diameter of 8-12 mm, for vertical (roof fans, air ducts, etc.) - one. The most common sling methods in Fig.8-Fig.26.

Fig.8. WPP-40.

Fig.9. Radial fan

Fig.10. Locking fans C4-70

Fig.11. Slingering the top of the casing of fans c4-70

Fig.12. Lowering the lower part of the casing of the fan c4-70

Fig.13. Slinger of shaft with fan frames C470

Fig.14. Terminating axial fan

Fig.15. VKR-6.3 fan

Fig.16. Air-thermal curtain a6,3

Fig.17. Scrubber

Fig.18. Cyclone type TN.

Fig.19. EKF irrigation chambers

Fig.20. Ventagregate drive

Fig.21. Wheel and guide apparatus in casing

Fig.22. Air Filter FR-3

Fig.23. Slinger of packaging valve

Fig.24. Slinger of packaging Cameras CO and VK

Fig.25. Locking air duct

Fig.26. Locking of the enlarged node

3.4.7. The completion of the preparatory work is recorded in the general journal of work (the recommended form is given in the RD 11-05-2007) and should be taken on the act on the implementation of safety safety measures, decorated according to the annex and, SNiP 12-03-2001.

3.5. Installation of air ducts

3.5.1. The method of installation of air ducts should be chosen depending on their position (horizontal, vertical), placement relative to the structures (inside or outside the building, in the wall, in the columns, in the interferenny space, in the mine, on the roof of the building) and the nature of the building (one- or multi-storey , industrial, public, etc.).

3.5.2. As a shaped parts of a complex geometric shape, as well as to attach the ventilation equipment, air distributors, noiselessness and other devices located in tailcases, chambers, etc., flexible air ducts from fiberglass, metal-in-room, aluminum foil, etc. Application should be used. Flexible air ducts as direct links are not allowed.

In order to reduce the aerodynamic resistance, the details from flexible sleeves in the mounted position should have a minimal degree of compression.

3.5.3. Installation of metal air ducts should be carried out, as a rule, enlarged blocks in the following sequence:

- marking of the installation of air duct fixtures;

- installation of fixtures;

- coordination with builders of location locations and methods for fastening lifting facilities and their installation;

- delivery to the place of installation of duct details, check of completeness and quality;

- assembly of parts of air ducts in enlarged blocks;

- installation of the block into the design position and consolidate it;

- installation of plugs on the upper ends of vertical air ducts located at an altitude of up to 1.5 m from the floor.

3.5.4. The block length is determined by the size of the section and the type of air duct connections, installation conditions and the presence of lifting facilities.

The length of the enlarged blocks of horizontal air ducts connected on the flanges should not exceed 20 m.

3.5.5. The schemes of the organization's organization during installation of air ducts are given in Fig.27-Fig.30.

Fig.27. Scheme of the organization of the working area when installing air ducts on the outer wall of the building

1 - console with block; 2 - winch; 3 - autohydrotype; 4 - Traverse; 5 - delay; 6 - Block

Fig.28. Scheme of the organization of the working area when installing horizontal air ducts in the building

1 - winch; 2 - Traverse; 3 - enlarged duct assembly; 4 - Suspension

Fig.29. The scheme of the organization of the working area when installing horizontal air ducts on the overpass

1 2 - Traverse; 3 - truck crane; 4 - Avtohydrovant

Fig.30. Scheme of the organization of the working area when installing vertical air ducts on the outer wall of the building

1 - enlarged duct assembly; 2 - semi-automatic sling; 3 - winch; 4 - block; 5 - console; 6 - brackets; 7 - Stretching

Fig.31. Scheme of ventilation unit

P1.3 - Ventilation unit

3.5.6. Installation of fans should be made in the following sequence:

- acceptance of ventilation chambers;

- Delivery of fan or its separate parts to the place of installation;

- installation of lifting facilities;

- trowel fan or individual parts;

- rise and horizontal movement of the fan to the installation site;

- installation of the fan (fan assembly) on the support structures (foundation, platform, brackets);

- checking the correctness of the installation and assembly of the fan;

- fixing the fan to supporting structures;

- Checking the fan operation.

3.5.7. Air ducts are mounted regardless of the presence of technological equipment in accordance with the design bindings and marks. The addition of air ducts to technological equipment should be made after its installation.

3.5.8. Air ducts intended for transportation of moistened air should be mounted so that at the bottom of the air ducts there are no longitudinal seams.

3.5.9. Gaskets between the flanges of the air ducts should not appear inside the air ducts.

Gaskets must be made of the following materials:

- foam rubber, ribbon porous or monolithic rubber with a thickness of 4-5 mm or polymer mastic harness (PMZ) - for air ducts, according to which air, dust or waste of materials are moved to 343 K (70 ° C);

- asbestos cord or asbestos cardboard - with temperatures above 343 K (70 ° C);

- Acid-resistant rubber or acid-resistant gasket plastic - for air ducts, according to which air with acid pairs move.

To seal the inflaintse compounds of air ducts should be applied:

- the sealing tape "Gerlen" - for air ducts for which air is moved with a temperature of up to 40 ° C;

- Mastica "Bupetrol" - for round-section air ducts with a temperature of up to 70 ° C;

- thermal cuffs or ribbons - for round-section air ducts with a temperature of up to 60 ° C and other sealing materials, coordinated in the prescribed manner.

3.5.10. Bolts in flange connections must be tightened, all bolts nuts should be located on one side of the flange. When installing bolts vertically nuts, as a rule, should be located on the bottom side of the compound.

3.5.11. Fastening horizontal metal uninsulated air ducts (clamps, suspension, supports, etc.) on the Beschatine Connection It should be set at a distance of not more than 4.0 m from the other when the duct diameters of the round section or the size of the larger side of the rectangular duct less than 400 mm and at a distance of no more than 3.0 m from the other - when the ducts of the round section or the size of the larger side Air duct rectangular cross section 400 mm and more.

Fastening horizontal metal uninsulated air ducts on the flange compound The circular section with a diameter of up to 2000 mm or a rectangular section with the size of its main side up to 2000 mm inclusive should be set at a distance of no more than 6.0 m from the other. The distances between the fasteners of the isolated metal air ducts of any size of cross sections, as well as uninsulated round-section air ducts with a diameter of more than 2000 mm or a rectangular section, with the sizes of its main side, more than 2000 mm must be assigned to working documentation.

Clamps should cover metal ducts tightly.

3.5.12. Mounting vertical metal air ducts should be set at a distance of no more than 4.0 m from the other.

The mounting of vertical metal air ducts inside the premises of multi-storey buildings from the height of the floor to 4.0 m is performed in intermediate floors.

The mounting of vertical metal air ducts indoors from the floor height of more than 4.0 m is performed on the roof of the building.

When installing vertical air ducts from asbestos-cement fastening boxes, it should be installed after 3.0-4.0 m. When installing horizontal air ducts, you should install two mounts for each section at clutch compounds and one mount - with flaring connections. Fastening should be performed in the termination.

In vertical air ducts from fuse-tube boxes, the upper box is inserted into the socket of the bottom.

3.5.13. The attachment of stretch marks and suspensions directly to the flanges of the air duct is not allowed. The tension of adjustable suspensions should be uniform.

3.5.14. Freely suspended air ducts must be separated by installing double suspensions every two single suspensions at a suspension length from 0.5 to 1.5 m.

With the length of the suspension of more than 1.5 m, double suspensions should be installed through each single suspension.

3.5.15. Air ducts should be strengthened so that their weight is not transmitted to ventilation equipment.

Air ducts join fans through vibration-insulating flexible inserts from fiberglass or other material that provides flexibility, density and durability.

Vibration insulating flexible inserts should be installed directly before individual tests.

3.5.16. Pouring and coupling compounds are sealing the hemp harnesses, moistened in asbestos-cement solution with the additive of casein glue.

The free space of the termination or coupling is filled with asbestos-cement mastic.

Connection locations after rejection of mastic must be sealed with a cloth. The fabric should fit tightly to the box throughout the perimeter and should be painted with oil paint.

3.5.17. The air ducts made of polymer film should be suspended on steel rings from a wire with a diameter of 3-4 mm, located at a distance of no more than 2 m from the other.

The diameter of the rings should be 10% larger than the diameter of the duct. Steel rings should be fixed with a wire or a plate with a neckline to the carrying cable (wire) with a diameter of 4-5 mm, stretched along the axis of the air duct and fixed to the building structures every 20-30 m.

To eliminate the longitudinal movements of the air duct when filled with air, the polymer film should be pulled to the disappearance of the provisions between the rings.

3.5.18. When installing fans on metal structures, vibration insulators should be attached to them. Elements of metal structures that are attached to vibration and beolators should coincide in terms of the corresponding elements of the fan unit frame.

When installing on the rigid base, the fan bed should be tightly faced with soundproofing gaskets.

3.5.19. Radial fan shafts must be installed horizontally (roof fan shafts - vertically), vertical walls of centrifugal fans should not have distortion and tilt.

Gaskets for composite fans coverings should be used from the same material as gaskets for air ducts of this system.

3.5.20. Electric motors must be accurately adjusted with installed fans and secured. The axis of the pulleys of electric motors and fans during belt transmission must be parallel, and the middle lines of the pulleys must coincide.

Slasons of electric motors must be mutually parallel and installed in terms of level. The support surface of the sled should come into contact throughout the plane with the foundation.

Couplings and belt transmissions should be fencing.

3.5.21. A fan suction opening, not attached to the air duct, it is necessary to protect the metal grid with a cell size of no more than 70x70 mm.

3.5.22. The filter material of the plated filters must be stretched without provisions and wrinkles, as well as firmly lay down to the side walls. In the presence, on the filter material, the latter should be located on the side of air intake.

3.5.23. Flexible air ducts should be applied in accordance with the project (work project) as the shaped parts of the complex geometric shape, as well as to attach the ventilation equipment, air distributors, silencers and other devices located in the tail ceilings, cameras.

3.5.24. The fastening of the flanges on the air ducts of steel with a thickness of 0.5-1.5 mm should be carried out with the help of flaming, and with the thickness of the steel st. 1.5 mm - electric arc welding with a solid seam.

With thickness, more than 1 mM are allowed to fasten the flanges without flapping by taps by electric arc welding after 50-60 mm, followed by sealing of the gap between the flanges and the air ducts.

Methods of sealing should be determined by the technology of the manufacturer's enterprise.

3.5.25. Flabande air ducts must overlap the flange of at least 6 mm and should not block the bolted holes.

Through breakdowns are allowed not more than four on one end of the duct.

3.5.26. Flange fastening from moving them along the axis of the flange duct of the circular cross section with flange flanges should be carried out in any way with the mandatory provision of their rotation around the axis. At the same time, the flange must fit tightly to the mirror of the duct flange.

3.5.27. For the leaf air ducts, more than 1.5 mm thick, the flanges from the corner rolled should be welded from the inside, and the flanges are flat - from the outside of the product. At the same time, the edges of the ends of the air ducts should not be behind the flange mirror.

3.5.28. The final stage of installation of ventilation systems are their individual tests.

3.5.29. By the beginning of individual tests of systems, general construction and finishing works on ventilation cameras and mines should be completed, as well as finish the installation and individual tests of the means of ensuring (power supply, heat boat supply, etc.). In the absence of power supply of ventilation installations by a permanent diagram, the connection to the temporary diagram and the maintenance of the maintenance of the starting device is carried out by the General Contractor.

3.5.30. For each ventilation system, a passport is drawn up in two copies of

IV. Quality and Acceptance Requirements

4.1. Control and assessment of the quality of work on the installation of the duct system are performed in accordance with the requirements of regulatory documents:

- SP 48.13330.2011. "Snip 12-01-2004 Organization of construction. Actualized editors";

- Snip 3.05.01-85. Domestic sanitary systems;

- Snip 3.05.05-84. Technological equipment and technological pipelines.

4.2. Quality control of construction and installation work is carried out by specialists with the attraction of an accredited construction laboratory equipped with technical means that ensure the necessary accuracy and completeness of control and is assigned to the manufacturer of works or master work on the installation of the air duct system.

4.3. Construction quality control of work should include input control of project working documentation and engineering research results, as well as the quality of the preceding work, the operational control of construction and installation work, production processes or technological operations and acceptance control of work assessment performed.

4.4. Input control

4.4.1. Input control is carried out in order to identify deviations from project requirements and relevant standards. Input control of the construction materials, structures and products entering the object:

- the registration method by analyzing data recorded in documents (certificates, passports, invoices, etc.);

- external visual inspection (according to GOST 16504-81);

- technical inspection (according to GOST 16504-81);

- if necessary, the measuring method using measuring instruments (checking the main geometric parameters), incl. laboratory equipment;

- control tests in cases of doubts in the correctness of the characteristics or absence of the necessary data in certificates and passports of manufacturers.

4.4.2. Input control of incoming materials is carried out by the Commission appointed by order of the Director of the Construction Organization. The Commission includes a representative of the supply department, linear IER and production and technical department. The organization of input control, purchased products and materials is carried out in accordance with the instructions:

If the payment procedure on the payment system website was not completed, monetary
funds from your account will not be written off and payment confirmation We will not get.
In this case, you can repeat the purchase of the document using the button on the right.

An error has occurred

Payment was not completed due to technical error, cash from your account
They were not written off. Try wait a few minutes and repeat the payment again.